Taiwan Security Monitor

Taiwan Arms Sale Backlog, October 2026 Update

F-16s Begin Delivery!

Authors: Joseph Oโ€™Connor, Kayleigh Brown, Denzel Bell and TSM Staff


October 2026 was a busy month for the backlog, in contrast to a quiet September. In the first days of October, Taiwan received its first two F-16 Block 70s at Chihhang Air Base in Taitung, allowing a sale worth $8 billion to be moved to a status of โ€œin delivery.โ€ The Ministry of National Defense also released updates on three more backlogged items and released a report to the Legislative Yuan detailing the status of three arms sales cases they consider delayed. Two U.S. contract awards were also announced in October. This month, Congress received no new Foreign Military Sales (FMS) notifications for Taiwan, and no existing sales were fully delivered. The total value of FMS cases notified to Congress but not yet delivered to Taiwan has been adjusted to $30.16 billion, due to a reporting error that we explain below. 

Figure 1 shows how the backlog is divided among asymmetric weapons, traditional weapons, and munitions. Arms sales that are only partly delivered are marked in yellow-orange. Table 1 lists all arms sales in the backlog with the latest status updates. Partially delivered sales are shown in italics, while newly announced and fully delivered sales are marked in bold and underlined.ย Major changes to the backlog this month include the shifting of the F-16 sale to โ€œin delivery,โ€ and the addition of a previously removed sale of Stingers that we erroneously reported in December 2025 as having been fulfilled.ย 

F-16 Block 70s Begin Delivery 

On October 2, Taiwan received its first two F-16C/D Block 70 fighter jets, numbered 6727 and 6728, landing at Chihhang Air Base in Taitung. This brings to an end a months-long saga for initial delivery: we reported in August that the two jets had left Lockheed Martinโ€™s production facility in Greenville, South Carolina, and stopped in Fort Worth, Texas before appearing at Hickam Air Base in Honolulu, Hawaii. In early September, we reported that the jets took off from Hickam, before turning around and remaining there for most of the month. No official reason was given for the delay, but we continue to assess that a combination of generalized maintenance issues and weather considerations precluded a delivery in September. 

Speaking after the delivery, Minister of National Defense Wellington Koo stated that four additional jets had cleared acceptance, with two in training and two in testing. While unable to confirm how many jets could be delivered by the end of the year, Koo said the MND was continually working with U.S. counterparts to ensure the caseโ€™s execution. As we have confirmed two F-16s have been delivered out of a total of 66, this case has been changed to a status of โ€œin delivery,โ€ representing a shift of a case worth $8 billion.ย 

MND Releases Arms Sales Timeline Report to Legislative Yuanย 

Towards the end of October, the MND submitted a report to the Legislative Yuan (LY) detailing the status and timelines of U.S. arms sales. As of the time of writing, TSM has not independently found the report, but Taipei Times reported its key findings. The report, reaffirming prior disclosures to the LY, categorized three arms sales as โ€œdelayedโ€ or behind schedule: Mark 48 heavyweight torpedoes, F-16 Block 70 fighter jets, and AGM-154C Joint Standoff Weapon (JSOW) missiles. The remaining 21 sales, meanwhile, remain on schedule in the MNDโ€™s view. The MND’s view of delayed sales is much more conservative compared to our backlog, but we do recognize the MNDโ€™s categorization of those three sales as delayed, owing to the fact that those three have been backlogged for the longest periods. 

That same report, reported by Liberty Times on October 27, also indicated that full delivery of four remaining MS-110 reconnaissance pods would be completed by the end of 2026. This is consistent with previous reporting that the sale would be completed by 2026. We also reported in August that two pods were in Taiwan, with one being tested in Hualien. 

MND Provides Updates on HCDS, Volcano, Stinger Deliveriesย 

This month, the MND also provided key updates on deliveries of three systems, which were not discussed in their report to the LY. 

On October 7, MND officials confirmed that the first batch of missiles for the Harpoon Coastal Defense System (HCDS) would be delivered before the end of the year. The shore-based anti-ship system, consisting of 100 missile launchers, 25 radar trucks, and 400 missiles, is worth $2.37 billion and was officially notified to Congress in October 2020, marking its sixth birthday this month. This is a significant increase from prior deliveries, which we reported in May 2025 has consisted of at least five launchers and one radar truck. That same day, MND officials also confirmed that all 14 Volcano minelaying system vehicles would be delivered by the end of 2027 in one single batch, adding additional specificity to previous reporting which indicated the systems would simply be delivered โ€œsoon.โ€ 

Four days later, on October 11, MND officials stated that Taiwan would be receiving 500 Stinger man-portable air defense missiles and 178 launchers by the end of this year. This tranche is part of a larger planned acquisition program for 2,621 Stingers and 763 launchers, to be distributed among the Army (2,235 missiles and 657 launchers) and the Navy (295 missiles and 85 launchers).  

The 500 missiles appear to originate from two Stinger cases, originally notified to Congress in December 2015 and July 2019, and worth $440 million in total. In December 2025, we erroneously removed the sale, considering it fulfilled based on an estimated timeline for delivery provided by the MND and reported by Taiwanese media. We assess that those 500 missiles are the same 500 missiles here, and that follow-on batches of the remaining 2,121 missiles will be from a future Stinger case that has yet to be announced, as opposed to a โ€œplus-upโ€ of the existing cases. 

Contract Awardsย 

Two major U.S. contracts involving backlogged items were awarded in October: 

  • On October 1, the Air Force awarded General Atomics Aeronautical Systems a $38.77 million contract for contractor logistics support and sustainment for Taiwanโ€™s MQ-9B SeaGuardian unmanned aerial vehicles. Work will be performed in California and will be completed by August 2029. We reported in September that two MQ-9Bs out of a total of four were on the ground in Taiwan, undergoing assembly and testing by General Atomics.ย 
  • On October 28, the Air Force awarded CAE USA, Inc., a $14.80 million contract for contractor logistics support, including spares management, for Taiwanโ€™s F-16 Block 20 and Block 70 Mission Training Center program. Work will be performed at Chiayi, Chihhang, and Chiashan Air Bases in Taiwan, alongside Morris Air National Guard Base in Tucson, Arizona, and will be completed by January 2032.ย 

FMS Salesย 

As aforementioned, no FMS sales to Taiwan were notified to Congress this month. Starting this month, however, we will begin highlighting other FMS sales notified to Congress that overlap with backlogged items or otherwise affect Taiwan in some way. 

  • On October 2, a sale to Egypt of 2,020 FGM-148F Javelin anti-tank missiles, along with 200 Javelin Lightweight Command Launch Units (LwCLUs) worth $832 million was notified. This overlaps with a sale to Taiwan of 1,050 Javelin missiles and 70 CLUs notified in December 2025 worth $375ย million.ย 
  • On October 30, a sale to Ukraine of 500 PAC-3 Missile Segment Enhancement (MSE) air defense missiles, worth $2.1 billion, was notified. This overlaps with a sale to Taiwan of 102 PAC-3 MSE missiles worth $832 million, along with likely future sales of PAC-3 MSE to Taipei.ย 
Table 1
Itemized list of backlogged capabilities by weapons category, October 2026
Capability SoldDollar Value (In Millions)Share of total backlog, October 2026Current Status as of October 2026
Traditional$12,92742.86%
F-16C/D Block 70$8,00026.53%October 2026: First two F-16s (6727 and 6728) landed at Chihhang AB, Taitung. Minister Koo also stated that four additional jets had cleared acceptance, w/ two in training and two in testing.
Paladin Self-Propelled Howitzer$4,03013.36%May 2026: Liberty Times reports that deliveries of Paladins are expected to start in 2030, due to U.S. production delays.
F-16 IRST Systems$5001.66%December 2025: US DoD awarded an undefinitized contract action to Lockheed Martin for targeting pods, including 55 IRST pods for Taiwan. Work is expected to complete by June 2031.
MS-110 Recce Pods$3671.22%October 2026: MND report to LY on arms sales indicates four remaining MS-110 pods will be delivered by end of 2026.
MK 75 76mm Gun Mounts$300.10%No information since posting of Congressional notification.
Asymmetric$14,90349.42%
HIMARS (Announced December 2025)$4,05013.43%April 2026: MND issues procurement contract for โ€œlong-range precision strike systems,โ€ likely meaning HIMARS, worth US$3.92 billion, with estimated completion in December 2032. Lockheed Martin also received a contract for full-rate production of launchers for U.S. and FMS customers, including Taiwan.
Harpoon Coastal Defense System$2,3707.86%October 2026: MND officials confirm to press that the first batch of 100 total missiles would be delivered by the end of 2026.
National Advanced Surface-to-Surface Air Missile System (NASAMS)$1,1603.85%February 2026: Press reports citing MND sources repeated earlier reporting that Taiwan plans on purchasing 9 additional NASAMS systems and associated missiles. This appears to be one of the arms sales cases being held up by special procurement budget deadlock in the LY.
ALTIUS (Announced December 2025)$1,1003.65%August 2026: MND signs LOA for purchase of 1,554 700M loitering munitions and 478 600M ISR drones, finalizing deal.
Tactical Mission Network$1,0103.35%January 2026: LY votes to move a special procurement budget proposed by the TPP to committee for consideration. The bill would not fund the Tactical Mission Network, but would fund almost all other FMS cases notified to Congress in December 2025.
PAC-3 MSE Interceptors$8822.92%March 2026: MND officials stated that ongoing delivery of 102 MSE missiles should not be affected by conflict in the Middle East.
AN/TPS-77 and AN/TPS-78 Radar Systems$8282.75%September 2025: Taiwanese press report citing 2026 budget request says that all radar systems will be delivered by the end of 2028. TPS-77s scheduled to begin arriving in 2026; TPS-78s to begin arriving in 2027.
MQ-9B Unmanned Aircraft$6001.99%September 2026: Taiwanese media reported sighting first flight of MQ-9B from Hualien Air Base, out of two total that were assembled and tested in-country by General Atomics.
HIMARS (Announced December 2022)$5201.72%June 2026: Included in MND force structure plan, 18 launchers expected “soon,” consistent with reporting from February 2026.
Javelin Missiles$3751.24%April 2026: MND issues procurement contract for โ€œanti-armor missiles,โ€ likely meaning Javelin or TOW-2B missiles, worth US$162.75 million, with estimated completion in September 2030.
Air-Launched Harpoon Missiles$3551.18%January 2023: Press report indicates that missiles will be delivered by 2030.
TOW Missiles$3531.17%April 2026: MND issues procurement contract for โ€œanti-armor missiles,โ€ likely meaning Javelin or TOW-2B missiles, worth US$162.75 million, with estimated completion in September 2030.
Field Information Communications System$2800.93%June 2026: Taiwanese media reported on immediate combat readiness exercises featuring FICS-equipped vehicles alongside combat units. Reporting also indicated ROCA units had begun fielding FICS systems in February 2026, though it is unclear whether all have been delivered.
C4 Modernization$2650.88%No information since posting of Congressional notification.
Stinger Missiles (Announced July 2019)$2230.74%October 2026: MND officials confirm to press that 500 Stingers and 178 launchers would be delivered by the end of the year; part of a larger acquisition of 2,600 missiles.
Stinger Missiles (Announced December 2015)$2170.72%October 2026: MND officials confirm to press that 500 Stingers and 178 launchers would be delivered by the end of the year; part of a larger acquisition of 2,600 missiles.
Volcano Anti-Tank Mining System$1800.60%October 2026: MND officials confirm to press that all 14 vehicles would be delivered by the end of 2027 in a single batch.
Taiwan Advanced Tactical Data Link System Upgrade$750.25%August 2024: Taiwan’s E-Procurement System announced the award of a contract for the Link-16 system with completion date in 2026.
Switchblade 300 Loitering Missile System$600.20%September 2026: Taiwanese media reports that several Switchblades crashed during familiarity training in August, due to frequency-switching and signal disconnection errors. Same report also indicated final batch of Switchblades could arrive by end of September.
Munitions$2,3297.72%
AGM-84H SLAM-ER Missile$1,0083.34%December 2025: Taiwanese press report citing a publication by the LY’s budget office indicates a multi-year delay in finalizing details on cost and delivery schedule for AGM-84 missiles. Press report suggests that there is no finalized Letter of Offer and Acceptance (LOA) for this case, which would lay out a payment and delivery schedule.
F-16 Munitions$6192.05%August 2026: Liberty Times reports that all 100 AGM-88 HARM missiles have been “deployed,” and that AMRAAM missiles have also been delivered “in batches.”
Mk 48 Heavyweight Torpedoes (Announced June 2017)$2500.83%October 2026: MND report to LY on arms sales reiterates sale as “delayed.”
AGM-154C Joint Standoff Weapon$1860.62%October 2026: MND report to LY on arms sales reiterates sale as “delayed.”
Mk 48 Heavyweight Torpedoes (Announced May 2020)$1800.60%October 2026: MND report to LY on arms sales reiterates sale as “delayed.”
AIM-9X Block II Missiles$860.29%August 2026: Liberty Times reports that an “initial batch” of AIM-9X Block IIs have been delivered, out of a total of 140. This is an increase of 40 missiles from the initial Congressional notification.

Taiwan Arms Sale Backlog, September 2026 Update

F-16s Remained Delayed, in Shadow of Xi-Trump Summit 

Authors: Joe Oโ€™Connor, Kayleigh Brown, Denzel Bell, and TSM Staff 


September 2026 was a quiet month for the backlog, unlike August. What was thought to be the beginning of F-16 Block 70 delivery in early September resulted in another month of delays; a summit between Xi and Trump in Washington elicited little detail on ongoing or future arms sales to Taiwan. Three cases have minor updates this month, and four major U.S. contracts for backlog-related items or services were awarded this month, marking the end of fiscal year 2026. In September, Congress received no new Foreign Military Sales (FMS) notifications for Taiwan, and no existing sales were fully delivered. The total value of FMS cases notified to Congress but not yet delivered to Taiwan is still $29.72 billion. 

Figure 1 shows how the backlog is divided among asymmetric weapons, traditional weapons, and munitions. Arms sales that are only partly delivered are marked in yellow-orange. Table 1 lists all arms sales in the backlog with the latest status updates. Partially delivered sales are shown in italics, while newly announced and fully delivered sales are marked in bold and underlined.  

Starting this month, we have also released the arms sale backlog as an interactive tool, providing information on timelines for each case. Check it out here.

F-16 Block 70s Delivery Delayed Further

On September 7, Liberty Times reported that the first two Taiwanese F-16C/D Block 70 fighter jets in delivery to Taiwan (numbered 6727 and 6728) had taken off from Hickam Air Force Base in Honolulu, Hawaii, but returned that same day, for then-unknown reasons. The aircraft remained in Hawaii throughout the entirety of September, with CNA reporting on September 29 that the MND would announce a delivery date once one was confirmed. At that time, Koo stated that Taiwan might receive additional technical support or an extended warranty for the continued delay. 

It is our analysis that the F-16s remained delayed during September, including severe weather and typhoon threats in the Western Pacific and generalized maintenance issues. Despite the coincidence of the F-16s eventually being delivered after the Xi-Trump summit in late September, we do not consider the delay to have been โ€œheldโ€ or frozen by the administration. 

At the time of writing, the two F-16s were delivered to Taiwan on October 2, at approximately 1200 local, per CNA and other Taiwanese media outlets. Since this delivery occurred in October, we will discuss it, along with any future F-16 delivery developments, in the October backlog update.

Trump-Xi Summit Reveals Little on Arms Sales, But Worries Remain 

This month featured a bilateral summit between Chinese leader Xi Jinping and President Trump on September 24 in Washington. Consisting mostly of economic policy discussions, arms sales to Taiwan did not feature prominently in the summit, and neither state explicitly mentioned arms sales in their readouts after the meeting. 

Before the summit, on September 12, Kyodo News reported that Beijing threatened to cancel the summit if the U.S. approved new arms sales to Taiwan, referring to a potential $14 billion package of equipment. On September 19, CNA reported that Anduril co-founder Palmer Luckey personally raised the stalled package with President Trump, Vice President JD Vance, and Secretary of State Marco Rubio, noting his companyโ€™s business with Taipei.  

Two days before the summit, on September 22, Reuters exclusively reported that Xi would press Trump on halting new arms sales and pausing current sales in delivery, also invoking the 1982 U.S.-China joint communique. The next day, September 23, Secretary of State Rubio told the press that pending arms sales to Taiwan remain under review as Washington weighs requirements against current stockpiles and production capacity.  

As previously stated, the summit day itself featured little to no publicly reported discussion on arms sales. In statements and an interview with Fox News on September 27, U.S. Ambassador to China David Perdue stated that there had been โ€œno change in the Taiwan policy.โ€ Perdue also revealed that during the summit, Trump offered to sell arms to the PRC. The latter statement, reported by the Financial Times, is worrying, but was likely a gaffe on Trumpโ€™s part, who later confirmed to the press that he had mentioned it to Xi. 

Broadly stated, this represents a continuation of the status quo since last month, and the stalled $14 billion package was originally publicly reported in February 2026. Other commentators, including Zach Cooper at the American Enterprise Institute, stated that based on the summit and planned future summits between Trump and Xi, he โ€œcannot imagineโ€ the Trump administration moving forward with the package until early 2027 at the earliest. While we do not forecast when exactly the package might be notified to Congress, we agree with this assessment, particularly since this latest summit resulted in two additional meetings in 2026, one at APEC in November and again at the G20 in December. 

Updates on ALTIUS, MQ-9Bs, MK48 Torpedoes 

Various updates also emerged about the following sales this month: 

  • ALTIUS: On September 10, Liberty Times reported that a prior sale of ALTIUS-600M loitering munitions to the ROC Army arrived in March 2026 without chargers due to the components being made in China, causing U.S. technical personnel to arrive in the country in order to service the systems. This is notable, as a larger batch of over 2,000 ALTIUS-700M and ALTIUS-600ISR unmanned systems are also en route to Taiwan, and issues in their auxiliary supply chains may cause problems in the future if a non-Chinese alternative is not able to be produced quickly. 
  • Switchblade 300 Loitering Missile System: On September 19, UpMedia reported that during familiarity training in Taiwan in August on Switchblade 300 loitering missile systems, several units crashed due to signal disconnection and frequency-hopping issues. In reporting on the Switchbladeโ€™s case history, UpMedia also reported that the final batch of Switchblades were scheduled to be delivered by the end of September. At the time of writing, TSM cannot independently verify that claim. 
  • Mk 48 Heavyweight Torpedoes: On September 23, Zona Militar reported that Mk 48 heavyweight torpedoes could arrive in Taiwan before the end of 2026, allowing additional testing of the indigenously produced Hai Kun submarine to move forward. Citing the president of the Taiwan Security Development Association, this reporting differs from prior reporting from the MND indicating that deliveries would not begin until 2027. 

Contract Awards 

Four major U.S. contracts involving backlog items were awarded, all by the Air Force, in September: 

On September 8, the Air Force awarded Pratt and Whitney, a Raytheon subsidiary, a $19.31 million contract for contractor engineering and support services until organic engineering capability is developed for Taiwan and 10 other FMS customers. Work is expected to be completed by March 2029. TSM estimates that these services likely apply to Taiwan’s existing fleet of F-16A/B Block 20 fighter jets, which have Pratt and Whitney-manufactured engines. 

On September 22, the Air Force awarded Raytheon a $105.65 million contract modification for Advanced Medium-Range Air-to-Air Missile (AMRAAM) parts purchases. This is an extension of a contract originally awarded in September 2025 and involves Taiwan alongside 28 other FMS customers. Work is expected to be completed by August 2027. In August, we reported that the initial batch of 200 AMRAAMs was in delivery to Taiwan. 

Six days later, on September 28, the Air Force also awarded Raytheon a $20.70 billion undefinitized contract action for AMRAAM all-up rounds and guidance section procurement. This action involves FMS sales to Taiwan and 15 other customers. Work is expected to be completed by June 2033. An undefinitized contract action means that a final contract or price has not been confirmed, but authorizes production. 

On September 30, the U.S. Air Force jointly awarded 21 companies a $2.4 billion total contract for repair, overhaul, and manufacture of parts for F100-PW-220/229 aircraft engines. This contract involves FMS sales to Taiwan and 28 other countries. Work is expected to be completed by September 2036. The F100-PW-220/229 engine is used in F-15 and F-16 fighter jets. 

Table 1
Itemized list of backlogged capabilities by weapons category, September 2026
Capability SoldDollar Value (In Millions)Share of total backlog, September 2026Current Status as of September 2026
Traditional$14,92743.50%
F-16C/D Block 70$8,00026.92%September 2026: Taiwanese media reports first two jets (6727 and 6728) took off from Hickam AFB in Hawaii, then returned. Jets remained in Hawaii, MND stated it would provide update on delivery date.
Paladin Self-Propelled Howitzer$4,03013.56%May 2026: Liberty Times reports that deliveries of Paladins are expected to start in 2030, due to U.S. production delays.
F-16 IRST Systems$5001.68%December 2025: US DoD awarded an undefinitized contract action to Lockheed Martin for targeting pods, including 55 IRST pods for Taiwan. Work is expected to complete by June 2031.
MS-110 Recce Pods$3671.24%August 2026: Pod sighted on F-16V around Jiashan Air Base, Taitung, undergoing first test of pod since arriving in Taiwan.
MK 75 76mm Gun Mounts$300.10%No information since posting of Congressional notification.
Asymmetric$14,76348.67%
HIMARS (Announced December 2025)$4,05013.63%April 2026: MND issues procurement contract for โ€œlong-range precision strike systems,โ€ likely meaning HIMARS, worth US$3.92 billion, with estimated completion in December 2032. Lockheed Martin also received a contract for full-rate production of launchers for U.S. and FMS customers, including Taiwan.
Harpoon Coastal Defense System$2,3707.97%August 2026: MND made final award for contract to transport HCDS equipment from US to Taiwan, worth $7.8 million and expected between August 2026 and July 2028.
National Advanced Surface-to-Surface Air Missile System (NASAMS)$1,1603.90%February 2026: Press reports citing MND sources repeated earlier reporting that Taiwan plans on purchasing 9 additional NASAMS systems and associated missiles. This appears to be one of the arms sales cases being held up by special procurement budget deadlock in the LY.
ALTIUS (Announced December 2025)$1,1003.70%August 2026: MND signs LOA for purchase of 1,554 700M loitering munitions and 478 600M ISR drones, finalizing deal.
Tactical Mission Network$1,0103.40%January 2026: LY votes to move a special procurement budget proposed by the TPP to committee for consideration. The bill would not fund the Tactical Mission Network, but would fund almost all other FMS cases notified to Congress in December 2025.
PAC-3 MSE Interceptors$8822.97%March 2026: MND officials stated that ongoing delivery of 102 MSE missiles should not be affected by conflict in the Middle East.
AN/TPS-77 and AN/TPS-78 Radar Systems$8282.79%September 2025: Taiwanese press report citing 2026 budget request says that all radar systems will be delivered by the end of 2028. TPS-77s scheduled to begin arriving in 2026; TPS-78s to begin arriving in 2027.
MQ-9B Unmanned Aircraft$6002.02%September 2026: Taiwanese media reported sighting first flight of MQ-9B from Hualien Air Base, out of two total that were assembled and tested in-country by General Atomics.
HIMARS (Announced December 2022)$5201.75%June 2026: Included in MND force structure plan, 18 launchers expected “soon,” consistent with reporting from February 2026.
Javelin Missiles$3751.26%April 2026: MND issues procurement contract for โ€œanti-armor missiles,โ€ likely meaning Javelin or TOW-2B missiles, worth US$162.75 million, with estimated completion in September 2030.
Air-Launched Harpoon Missiles$3551.19%January 2023: Press report indicates that missiles will be delivered by 2030.
TOW Missiles$3531.19%April 2026: MND issues procurement contract for โ€œanti-armor missiles,โ€ likely meaning Javelin or TOW-2B missiles, worth US$162.75 million, with estimated completion in September 2030.
Field Information Communications System$2800.94%June 2026: Taiwanese media reported on immediate combat readiness exercises featuring FICS-equipped vehicles alongside combat units. Reporting also indicated ROCA units had begun fielding FICS systems in February 2026, though it is unclear whether all have been delivered.
C4 Modernization$2650.89%No information since posting of Congressional notification.
Volcano Anti-Tank Mining System$1800.61%June 2026: Included in MND force structure plan, full order of 14 systems expected to ship “soon,” then be organized into “mobile interdiction teams” once in Taiwan, consistent with prior reporting.
Taiwan Advanced Tactical Data Link System Upgrade$750.25%August 2024: Taiwan’s E-Procurement System announced the award of a contract for the Link-16 system with completion date in 2026.
Switchblade 300 Loitering Missile System$600.20%September 2026: Taiwanese media reports that several Switchblades crashed during familiarity training in August, due to frequency-switching and signal disconnection errors. Same report also indicated final batch of Switchblades could arrive by end of September.
Munitions$2,3297.84%
AGM-84H SLAM-ER Missile$1,0083.39%December 2025: Taiwanese press report citing a publication by the LY’s budget office indicates a multi-year delay in finalizing details on cost and delivery schedule for AGM-84 missiles. Press report suggests that there is no finalized Letter of Offer and Acceptance (LOA) for this case, which would lay out a payment and delivery schedule.
F-16 Munitions$6192.08%August 2026: Liberty Times reports that all 100 AGM-88 HARM missiles have been “deployed,” and that AMRAAM missiles have also been delivered “in batches.”
Mk 48 Heavyweight Torpedoes (Announced June 2017)$2500.84%September 2026: Reporting citing Taiwanese think tank states Mk 48s should begin delivery by the end of 2026, allowing further Hai Kun testing.
AGM-154C Joint Standoff Weapon$1860.62%August 2026: Liberty Times reports that JSOW delivery continues to be delayed until “between 2027 or 2028.”
Mk 48 Heavyweight Torpedoes (Announced May 2020)$1800.61%September 2026: Reporting citing Taiwanese think tank states Mk 48s should begin delivery by the end of 2026, allowing further Hai Kun testing.
AIM-9X Block II Missiles$860.29%August 2026: Liberty Times reports that an “initial batch” of AIM-9X Block IIs have been delivered, out of a total of 140. This is an increase of 40 missiles from the initial Congressional notification.

Taiwan Arms Sale Backlog, August 2026 Update

Jets and Munitions Begin Delivery

Author: Joe Oโ€™Connor & TSM Staff


August 2026, unlike July, showed quite a bit of activity regarding the backlog, including the near-imminent delivery of the F-16C/D Block 70s and ongoing deliveries of munitions for the F-16. Taiwanโ€™s Ministry of National Defense (MND) also announced updates relating to Harpoon Coastal Defense Systems and additional ALTIUS unmanned systems. In August, Congress received no new Foreign Military Sales (FMS) notifications for Taiwan, and no existing sales were fully delivered. The total value of FMS cases notified to Congress but not yet delivered to Taiwan is still $29.72 billion.

Figure 1 shows how the backlog is divided among asymmetric weapons, traditional weapons, and munitions. Arms sales that are only partly delivered are marked in yellow-orange. Table 1 lists all arms sales in the backlog with the latest status updates. Partially delivered sales are shown in italics, while newly announced and fully delivered sales are marked with bold and underlining. 

F-16 Block 70s Start Delivery Flights

On 26 August, Liberty Times reported that the first two Taiwanese F-16C/D Block 70 fighter jets were in transit from the United States to Zhihang Air Base in Taitung. The two jets, numbered 6727 and 6728, reportedly left Lockheed Martin production facilities in Greenville, South Carolina on 17 August, arriving in Honolulu, Hawaii, on 21 August. On 25 August, the two jets arrived at Guam, their last probable stop before arriving in Taiwan. Reporting has indicated that a combination of bad weather around Taiwan and potential mechanical issues has resulted in a delay of the ferry flights.

Because TSM was not able to verify the presence of these two aircraft at Zhihang, an event that would have been reported extensively by the Taiwanese press, we will not be marking the F-16 Block 70 as in delivery for August. Owing to the sale representing $8 billion or roughly 25% of the entire backlog topline, we consider this too important to remove until the first airframes actually arrive on the island.

F-16 Munitions Reported as Partially Delivered

Additional reporting on 20 August detailing preparations for the arrival of F-16s in Taiwan revealed that several sales of munitions for the jets are in progress. An initial batch of AIM-9X Block II Sidewinder air-to-air missiles has already arrived, out of approximately 140 expected in total. The Sidewinder sale was notified to Congress in September 2022 and is worth approximately $86 million. 

The same report also indicated that all 100 AGM-88 High-Speed Anti-Radiation Missiles (HARMs) โ€œhave been fully deployed.โ€ Initial batches of AIM-120-C8 Advanced Medium-Range Air-to-Air Missiles (AMRAAMs), out of 200 total, are also in delivery. Combined, the HARMs and AMRAAMs represent a sale of โ€œF-16 Munitionsโ€ notified to Congress in March 2023, valued at $619 million. Since both are still in delivery, we have reflected that in Figure 1 and Table 1, for an additional $705 million of items in delivery this month.

The same reporting on the above salesโ€™ delivery statuses also confirmed prior reporting about massive delays in delivery of AGM-154 Joint Standoff Weapons (JSOW) air-to-ground missiles, noting that delivery would not occur until โ€œbetween 2027 and 2028.โ€ The JSOW sale, the most-delayed sale in the backlog, having been notified to Congress in June 2017, will have been in the pipeline to Taipei for nearly a decade before deliveries even begin, if timelines stay consistent.

Updates on HCDS, ALTIUS Sales, MS-110 Pods

Various updates also emerged about the following sales this month:

HCDS:

On 4 August, the MND made a final contract award for transport of Harpoon Coastal Defense System equipment from manufacturing facilities in the United States to Taiwan. Worth NT$250 million (US$7.8 million), the performance period is scheduled to run from 1 August 2026 to 31 July 2028, indicating that deliveries will end by mid-2028.

ALTIUS:

On 27 August, the MND signed a Letter of Offer and Acceptance (LOA) for the sale of 1,554 ALTIUS-700M loitering munitions and 478 ALTIUS-600M ISR drones, a sale notified in December 2025 worth approximately US$1.1 billion. The final contract award posted on Taiwanโ€™s E-Procurement System, worth NT$26.9 billion (US$876 million) is expected to represent the costs for the physical systems themselves, per Liberty Times reporting. Additionally, the drones are expected to be delivered by the fourth quarter of 2026, but the final delivery deadline was reportedly extended to 2033.

MS-110 Recce Pods:

On 26 August, Liberty Times reported that a ROCAF F-16V carrying an MS-110 reconnaissance pod was sighted around Jiashan Air Base in Hualien, in its first test by the Taiwanese Air Force. While the report did not provide any update on the delivery status (TSM estimates that the sale remains in delivery until otherwise stated), the test remains a good indicator of Taipeiโ€™s desire to integrate incoming systems with existing airframes as soon as they arrive on the island.

Contract Awards

One notable US contract award involving a Taiwan backlog item appeared this month. On 17 August, the U.S. Air Force awarded Lockheed Martin a $31.29 million contract for โ€œadvisory engineering and technical servicesโ€ for an undisclosed program. This involved FMS customers, including Taiwan and 10 other countries, all of whom own and operate F-16 fighter jets. Based on that, TSM assesses that this is for engineering services for F-16 Block 70s in Taiwanโ€™s case and other F-16 variants for other FMS customers. 

Table 1
Itemized list of backlogged capabilities by weapons category, August 2026
Capability SoldDollar Value (In Millions)Share of total backlog, July 2026Current Status as of August 2026
Traditional$12,92743.50%
F-16C/D Block 70$8,00026.92%August 2026: First two jets (6727 and 6728) en route to Taiwan, leaving production facility on 17 Aug, reaching Hawaii on 21 Aug, and reaching Guam 25 Aug. Jets not arrived in Taitung by end of August.
Paladin Self-Propelled Howitzer$4,03013.56%May 2026: Liberty Times reports that deliveries of Paladins are expected to start in 2030, due to U.S. production delays.
F-16 IRST Systems$5001.68%December 2025: US DoD awarded an undefinitized contract action to Lockheed Martin for targeting pods, including 55 IRST pods for Taiwan. Work is expected to complete by June 2031.
MS-110 Recce Pods$3671.24%August 2026: Pod sighted on F-16V around Jiashan Air Base, Hualien, undergoing first test of pod since arriving in Taiwan.
MK 75 76mm Gun Mounts$300.10%No information since posting of Congressional notification.
Asymmetric$14,46348.67%
HIMARS (Announced December 2025)$4,05013.63%April 2026: MND issues procurement contract for โ€œlong-range precision strike systems,โ€ likely meaning HIMARS, worth US$3.92 billion, with estimated completion in December 2032. Lockheed Martin also received a contract for full-rate production of launchers for U.S. and FMS customers, including Taiwan.
Harpoon Coastal Defense System$2,3707.97%August 2026: MND made final award for contract to transport HCDS equipment from US to Taiwan, worth $7.8 million and expected between August 2026 and July 2028.
National Advanced Surface-to-Surface Air Missile System (NASAMS)$1,1603.90%February 2026: Press reports citing MND sources repeated earlier reporting that Taiwan plans on purchasing 9 additional NASAMS systems and associated missiles. This appears to be one of the arms sales cases being held up by special procurement budget deadlock in the LY.
ALTIUS (Announced December 2025)$1,1003.70%August 2026: MND signs LOA for purchase of 1,554 700M loitering munitions and 478 600M ISR drones, finalizing deal.
Tactical Mission Network$1,0103.40%January 2026: LY votes to move a special procurement budget proposed by the TPP to committee for consideration. The bill would not fund the Tactical Mission Network, but would fund almost all other FMS cases notified to Congress in December 2025.
PAC-3 MSE Interceptors$8822.97%March 2026: MND officials stated that ongoing delivery of 102 MSE missiles should not be affected by conflict in the Middle East.
AN/TPS-77 and AN/TPS-78 Radar Systems$8282.79%September 2025: Taiwanese press report citing 2026 budget request says that all radar systems will be delivered by the end of 2028. TPS-77s scheduled to begin arriving in 2026; TPS-78s to begin arriving in 2027.
MQ-9B Unmanned Aircraft$6002.02%June 2026: Unknown number of drones in Taiwan undergoing assembly and pre-delivery flight testing b/n MND and manufacturer. Also included in MND force structure plan, drones and ground equipment expected to be shipped between July and September 2026.
HIMARS (Announced December 2022)$5201.75%June 2026: Included in MND force structure plan, 18 launchers expected “soon,” consistent with reporting from February 2026.
Javelin Missiles$3751.26%April 2026: MND issues procurement contract for โ€œanti-armor missiles,โ€ likely meaning Javelin or TOW-2B missiles, worth US$162.75 million, with estimated completion in September 2030.
Air-Launched Harpoon Missiles$3551.19%January 2023: Press report indicates that missiles will be delivered by 2030.
TOW Missiles$3531.19%April 2026: MND issues procurement contract for โ€œanti-armor missiles,โ€ likely meaning Javelin or TOW-2B missiles, worth US$162.75 million, with estimated completion in September 2030.
Field Information Communications System$2800.94%June 2026: Taiwanese media reported on immediate combat readiness exercises featuring FICS-equipped vehicles alongside combat units. Reporting also indicated ROCA units had begun fielding FICS systems in February 2026, though it is unclear whether all have been delivered.
C4 Modernization$2650.89%No information since posting of Congressional notification.
Volcano Anti-Tank Mining System$1800.61%June 2026: Included in MND force structure plan, full order of 14 systems expected to ship “soon,” then be organized into “mobile interdiction teams” once in Taiwan, consistent with prior reporting.
Taiwan Advanced Tactical Data Link System Upgrade$750.25%August 2024: Taiwan’s E-Procurement System announced the award of a contract for the Link-16 system with completion date in 2026.
Switchblade 300 Loitering Missile System$600.20%September 2025: Taiwanese press reported details of delivery schedule: 66 drones already delivered to Military Police Command; 150 drones expected to be delivered to ROC Army by end of 2025, 469 drones by the end of 2026.
Munitions$2,3297.84%
AGM-84H SLAM-ER Missile$1,0083.39%December 2025: Taiwanese press report citing a publication by the LY’s budget office indicates a multi-year delay in finalizing details on cost and delivery schedule for AGM-84 missiles. Press report suggests that there is no finalized Letter of Offer and Acceptance (LOA) for this case, which would lay out a payment and delivery schedule.
F-16 Munitions$6192.08%August 2026: Liberty Times reports that all 100 AGM-88 HARM missiles have been “deployed,” and that AMRAAM missiles have also been delivered “in batches.”
Mk 48 Heavyweight Torpedoes (Announced June 2017)$2500.84%July 2026: Taiwanese media reported that due to ongoing delays, the MND was considering “borrowing active inventory torpedoes from the U.S. military.”
AGM-154C Joint Standoff Weapon$1860.62%August 2026: Liberty Times reports that JSOW delivery continues to be delayed until “between 2027 or 2028.”
Mk 48 Heavyweight Torpedoes (Announced May 2020)$1800.61%July 2026: Taiwanese media reported that due to ongoing delays, the MND was considering “borrowing active inventory torpedoes from the U.S. military.”
AIM-9X Block II Missiles$860.29%August 2026: Liberty Times reports that an “initial batch” of AIM-9X Block IIs have been delivered, out of a total of 140. This is an increase of 40 missiles from the initial Congressional notification.

Taiwan Arms Sale Backlog, July 2026 Update

A Quiet Month

Authors: Joe O’Connor & TSM Staff


July 2026 was exceedingly quiet on the backlog front, with little to no updates on the status of delayed cases. Reports emerged that Taiwanโ€™s F-16 Block 70s would not be delivered with electronic warfare systems due to delays, and a Field Information Communications System was spotted during an ROCA exercise, confirming prior reporting of its delivery. In July, Congress received no new Foreign Military Sales (FMS) notifications for Taiwan, and no existing sales were fully delivered. The total value of FMS cases notified to Congress but not yet delivered to Taiwan is still $29.72 billion.

Figure 1 shows how the backlog is divided among asymmetric weapons, traditional weapons, and munitions. Arms sales that are only partly delivered are marked in yellow-orange. Table 1 lists all arms sales in the backlog with the latest status updates. Partially delivered sales are shown in italics, while newly announced and fully delivered sales are marked with bold and underlining. 

F-16 Block 70s to be Delivered Without EW Systems

Reporting from Taiwanese outlet UpMedia in July indicated that the first batch of Taiwanโ€™s 66 F-16C/D Block 70 fighter aircraft, set to be delivered soon, will not have the embedded AN/ALQ-254(V)1 electronic warfare system known as โ€œViper Shieldโ€ installed, due to production delays. The Viper Shield, an optional system alongside the standard AN/APG-83 Active Electronically Scanned Array (AESA) radar, is embedded directly in the fuselage rather than installed as a removable external pod on the aircraft.

Produced by American contractor L3Harris, the system has run into delays owing to its embedded nature as well as component bottlenecks, per UpMedia. A competing system designed by Northrop Grumman, known as the Integrated Viper Electronic Warfare Suite (IVEWS), is also in testing but remains in the development phase, signaling the urgent need for this system in new F-16s.

FICS Makes Appearance at June Exercise

On June 22, a Field Information Communications System (FICS)-installed Humvee was sighted in a Taiwanese Army 269th Brigade convoy during an โ€œimmediate combat readiness exerciseโ€ in Taoyuan. This marks the first documented public image of FICS in months and corroborates earlier reporting from 2026, which stated that the Army had โ€œnewly received/fieldedโ€ some of the systems, and that full delivery was expected to be completed by 2027.

Eagle-eyed backlog followers will recall that the FICS has been designated as partially delivered since February 2026, when we expanded the โ€œpartially deliveredโ€ designation to include all sales, not just those above $1 billion, as was the prior policy. As a result, it is unclear exactly when the FICS system began deliveries. The sale itself, worth $280 million, was notified to Congress in December 2020, and an MND budget unfreezing report from May 2025 indicated that testing had been completed and the first batch of equipment would arrive in the fourth quarter of 2025. TSM has not been able to independently verify the expected delivery date, but due to the presence of FICS in Taiwan, we will continue to mark that sale as partially delivered.

MK-48 Torpedoes Remain Delayed, MND Searching for Alternatives

As previously reported, the delivery timelines for Taiwanโ€™s two tranches of MK 48 heavyweight torpedoes have slipped into 2027-28, ending in 2030, but reporting in July indicated that the MND was searching for alternatives to procure torpedoes sooner, including โ€œborrowing active inventory torpedoes from the U.S. military” as an option. A military source also told Liberty Times that, after reviewing the international market, maintaining delayed procurement timelines for U.S. MK 48s remains more beneficial, as Taiwanโ€™s indigenous Hai Kun submarine, still in testing, has systems specifically designed to meet MK 48 standards, not European or Japanese torpedo variants.

Contract Awards

Two fairly minor but important contracts involving backlogged cases were awarded in July. On July 15, the Army awarded a $439 million undefinitized contract action for procurement of Army Tactical Missile System (ATACMS) missiles for Taiwan, specifically for use by HIMARS systems. Work will be performed by Lockheed Martin and completed by February 2031.

On July 24, the Air Force awarded a $332 million contract to Rockwell Collins ESA Vision Systems for spare and repair parts for the Joint Helmet Mounted Cueing System, a helmet-mounted heads-up display used on F-15, F-16, and F-18 fighter jets. These are likely for Taiwanโ€™s existing F-16 fleet and expanded Block 70 fleet, and work is expected to be completed by July 2032.

Table 1
Itemized list of backlogged capabilities by weapons category, July 2026
Capability SoldDollar Value (In Millions)Share of total backlog, July 2026Current Status as of July 2026
Traditional$12,92743.50%
F-16C/D Block 70$8,00026.92%July 2026: Taiwanese media reported that Taiwan’s F-16s would be delivered without the AN/ALQ-254(V)1 Viper Shield electronic warfare suite, due to delays in production by U.S. manufacturer L3Harris.
Paladin Self-Propelled Howitzer$4,03013.56%May 2026: Liberty Times reports that deliveries of Paladins are expected to start in 2030, due to U.S. production delays.
F-16 IRST Systems$5001.68%December 2025: US DoD awarded an undefinitized contract action to Lockheed Martin for targeting pods, including 55 IRST pods for Taiwan. Work is expected to complete by June 2031.
MS-110 Recce Pods$3671.24%June 2026: Included in MND force structure plan, expected to be delivered through end of 2026, confirming prior reporting from February indicating delivery of three pods by end of year.
MK 75 76mm Gun Mounts$300.10%No information since posting of Congressional notification.
Asymmetric$14,46348.67%
HIMARS (Announced December 2025)$4,05013.63%April 2026: MND issues procurement contract for โ€œlong-range precision strike systems,โ€ likely meaning HIMARS, worth US$3.92 billion, with estimated completion in December 2032. Lockheed Martin also received a contract for full-rate production of launchers for U.S. and FMS customers, including Taiwan.
Harpoon Coastal Defense System$2,3707.97%June 2026: Included in MND force structure plan, large number expected “soon,” confirming prior reporting delivery of 100 Harpoon missiles by end of 2026.
National Advanced Surface-to-Surface Air Missile System (NASAMS)$1,1603.90%February 2026: Press reports citing MND sources repeated earlier reporting that Taiwan plans on purchasing 9 additional NASAMS systems and associated missiles. This appears to be one of the arms sales cases being held up by special procurement budget deadlock in the LY.
ALTIUS (Announced December 2025)$1,1003.70%January 2026: MND reported that it would purchase 1,554 ALTIUS-700M loitering munitions and 478 ALTIUS-600M ISR drones. The FMS notification did not specify the number of drones being purchased.
Tactical Mission Network$1,0103.40%January 2026: LY votes to move a special procurement budget proposed by the TPP to committee for consideration. The bill would not fund the Tactical Mission Network, but would fund almost all other FMS cases notified to Congress in December 2025.
PAC-3 MSE Interceptors$8822.97%March 2026: MND officials stated that ongoing delivery of 102 MSE missiles should not be affected by conflict in the Middle East.
AN/TPS-77 and AN/TPS-78 Radar Systems$8282.79%September 2025: Taiwanese press report citing 2026 budget request says that all radar systems will be delivered by the end of 2028. TPS-77s scheduled to begin arriving in 2026; TPS-78s to begin arriving in 2027.
MQ-9B Unmanned Aircraft$6002.02%June 2026: Unknown number of drones in Taiwan undergoing assembly and pre-delivery flight testing b/n MND and manufacturer. Also included in MND force structure plan, drones and ground equipment expected to be shipped between July and September 2026.
HIMARS (Announced December 2022)$5201.75%June 2026: Included in MND force structure plan, 18 launchers expected “soon,” consistent with reporting from February 2026.
Javelin Missiles$3751.26%April 2026: MND issues procurement contract for โ€œanti-armor missiles,โ€ likely meaning Javelin or TOW-2B missiles, worth US$162.75 million, with estimated completion in September 2030.
Air-Launched Harpoon Missiles$3551.19%January 2023: Press report indicates that missiles will be delivered by 2030.
TOW Missiles$3531.19%April 2026: MND issues procurement contract for โ€œanti-armor missiles,โ€ likely meaning Javelin or TOW-2B missiles, worth US$162.75 million, with estimated completion in September 2030.
Field Information Communications System$2800.94%June 2026: Taiwanese media reported on immediate combat readiness exercises featuring FICS-equipped vehicles alongside combat units. Reporting also indicated ROCA units had begun fielding FICS systems in February 2026, though it is unclear whether all have been delivered.
C4 Modernization$2650.89%No information since posting of Congressional notification.
Volcano Anti-Tank Mining System$1800.61%June 2026: Included in MND force structure plan, full order of 14 systems expected to ship “soon,” then be organized into “mobile interdiction teams” once in Taiwan, consistent with prior reporting.
Taiwan Advanced Tactical Data Link System Upgrade$750.25%August 2024: Taiwan’s E-Procurement System announced the award of a contract for the Link-16 system with completion date in 2026.
Switchblade 300 Loitering Missile System$600.20%September 2025: Taiwanese press reported details of delivery schedule: 66 drones already delivered to Military Police Command; 150 drones expected to be delivered to ROC Army by end of 2025, 469 drones by the end of 2026.
Munitions$2,3297.84%
AGM-84H SLAM-ER Missile$1,0083.39%December 2025: Taiwanese press report citing a publication by the LY’s budget office indicates a multi-year delay in finalizing details on cost and delivery schedule for AGM-84 missiles. Press report suggests that there is no finalized Letter of Offer and Acceptance (LOA) for this case, which would lay out a payment and delivery schedule.
F-16 Munitions$6192.08%April 2026: Raytheon awards contract for full-rate production of AMRAAM-ER missiles for FMS customers, including Taiwan.
Mk 48 Heavyweight Torpedoes (Announced June 2017)$2500.84%July 2026: Taiwanese media reported that due to ongoing delays, the MND was considering “borrowing active inventory torpedoes from the U.S. military.”
AGM-154C Joint Standoff Weapon$1860.62%December 2025: MND report to LY on arms sale delivery status reiterates that AGM-154C is one of three delayed arms sales cases.
Mk 48 Heavyweight Torpedoes (Announced May 2020)$1800.61%July 2026: Taiwanese media reported that due to ongoing delays, the MND was considering “borrowing active inventory torpedoes from the U.S. military.”
AIM-9X Block II Missiles$860.29%March 2024: SIPRI annual update indicates delivery is expected to occur by 2030.

Taiwan Arms Sale Backlog, June 2026 Update

F-16s and MQ-9s Appear

Authors: Joe O’Connor & TSM Staff


Despite concerns in May about the future of arms sales to Taiwan, several backlogged sales made significant progress in June 2026, including continued F-16 flight testing and reports of MQ-9B drones being tested in Taiwan. A force structure plan released by Taiwanโ€™s Ministry of National Defense clarified near-term delivery timelines for other systems, giving us a good idea of what systems will arrive before the end of the year. In June, Congress received no new Foreign Military Sales (FMS) notifications for Taiwan, and no existing sales were delivered. The total value of FMS cases notified to Congress but not yet delivered to Taiwan is still $29.72 billion.

Figure 1 shows how the backlog is divided among asymmetric weapons, traditional weapons, and munitions. Arms sales that are only partly delivered are marked in yellow-orange. Table 1 lists all arms sales in the backlog with the latest status updates. Partially delivered sales are shown in italics, while newly announced and fully delivered sales are marked with bold and underlining. 

MQ-9B Testing in Taiwan Begins, F-16 Testing Continues

Most importantly, this month, reporting from CNA on June 21 indicated that an unknown number of MQ-9B SeaGuardian maritime surveillance drones were in Taiwan awaiting assembly and flight testing, in cooperation between the MND and General Atomics, the dronesโ€™ manufacturer. Since the drones are physically in Taiwan, we consider the MQ-9B case to be partially delivered until we receive confirmation that all four are there.

Flight testing in the U.S. for Taiwanโ€™s F-16C/D Block 70s continued in mid-June. Aviation watchers sighted the previously seen โ€œ6831โ€ tail number airframe flying from Lockheed Martin facilities in South Carolina to Fort Worth, Texas, for a fuel stop. The aircraft was carrying conformal fuel tanks, designed for longer-range flights, per Taiwan News reporting.

Both of these updates are encouraging developments. In particular, the MQ-9B flight testing and assembly taking place in Taiwan spells good news for direct cooperation between the MND and American defense contractors, and will hopefully condense timetables for future arms deliveries. Continued flights of F-16s also herald the first airframe arriving in Taiwan soon, a development we anticipate.

MND Releases Force Structure Plan with Delivery Timelines

A force structure plan released by the MND, also in mid-June, provided vague but notable timelines on some backlogged cases, seen below:

  • MS-110 Reconnaissance Pods: Expected to be delivered โ€œthrough the end of the year.โ€ This is consistent with prior reporting in our February 2026 update, which stated that three pods would arrive by the end of 2026.
  • Harpoon Coastal Defense System: โ€œA large numberโ€ would arrive โ€œsoon.โ€ Prior reporting from our February 2026 update indicated the delivery of an additional 100 Harpoon missiles by the end of 2026, bringing the total to 400 missiles. Both the force structure report and prior MND budget โ€œunfreezingโ€ reports confirm that HCDS support equipment, including 5 launcher vehicles and 1 radar truck, was already delivered in 2025.
  • MQ-9B SeaGuardian: Drones and ground control equipment are expected to be shipped between July and September. The above report indicates that the drones are already there.
  • HIMARS: Relating to the earlier sale notified in December 2022, 18 systems will arrive โ€œsoon.โ€ This is consistent with prior reporting from February 2026, indicating 18 launchers would arrive by the end of 2026.
  • M136 Volcano Anti-Tank Mining System: Full order is expected to ship โ€œsoon,โ€ then be organized into โ€œmobile interdiction teamsโ€ once combat-ready. Our reporting confirms that all 14 systems will likely be delivered by 2026.

Most of the updates in this force structure plan simply confirm prior reporting from earlier in 2026, but provide a more comprehensive list of what is expected before 2027.

Mk 48 Torpedoes Receive Delivery Update

The MND also confirmed in June that deliveries of MK 48 heavyweight torpedoes would begin with 28 in 2027 and 28 in 2028. This is somewhat consistent with prior reporting from September 2025, indicating that Taiwan would receive 14 each in 2027 and 2028. Interestingly, the MND stated that MK 48 deliveries would directly support the Hai Kun indigenous submarine program. Previously, both MK 48 cases have been marked by the MND and the Legislative Yuan (LY) as delayed.

Table 1
Itemized list of backlogged capabilities by weapons category, June 2026
Capability SoldDollar Value (In Millions)Share of total backlog, June 2026Current Status as of June 2026
Traditional$12,92743.50%
F-16C/D Block 70$8,00026.92%June 2026: Taiwanese F-16 spotted flying from production facility in South Carolina to Texas, likely conducting pre-delivery flight tests. F-16s also included in MND force structure plan indicating delivery between July and September 2026.
Paladin Self-Propelled Howitzer$4,03013.56%May 2026: Liberty Times reports that deliveries of Paladins are expected to start in 2030, due to U.S. production delays.
F-16 IRST Systems$5001.68%December 2025: US DoD awarded an undefinitized contract action to Lockheed Martin for targeting pods, including 55 IRST pods for Taiwan. Work is expected to complete by June 2031.
MS-110 Recce Pods$3671.24%June 2026: Included in MND force structure plan, expected to be delivered through end of 2026, confirming prior reporting from February indicating delivery of three pods by end of year.
MK 75 76mm Gun Mounts$300.10%No information since posting of Congressional notification.
Asymmetric$14,46348.67%
HIMARS (Announced December 2025)$4,05013.63%April 2026: MND issues procurement contract for โ€œlong-range precision strike systems,โ€ likely meaning HIMARS, worth US$3.92 billion, with estimated completion in December 2032. Lockheed Martin also received a contract for full-rate production of launchers for U.S. and FMS customers, including Taiwan.
Harpoon Coastal Defense System$2,3707.97%June 2026: Included in MND force structure plan, large number expected “soon,” confirming prior reporting delivery of 100 Harpoon missiles by end of 2026.
National Advanced Surface-to-Surface Air Missile System (NASAMS)$1,1603.90%February 2026: Press reports citing MND sources repeated earlier reporting that Taiwan plans on purchasing 9 additional NASAMS systems and associated missiles. This appears to be one of the arms sales cases being held up by special procurement budget deadlock in the LY.
ALTIUS (Announced December 2025)$1,1003.70%January 2026: MND reported that it would purchase 1,554 ALTIUS-700M loitering munitions and 478 ALTIUS-600M ISR drones. The FMS notification did not specify the number of drones being purchased.
Tactical Mission Network$1,0103.40%January 2026: LY votes to move a special procurement budget proposed by the TPP to committee for consideration. The bill would not fund the Tactical Mission Network, but would fund almost all other FMS cases notified to Congress in December 2025.
PAC-3 MSE Interceptors$8822.97%March 2026: MND officials stated that ongoing delivery of 102 MSE missiles should not be affected by conflict in the Middle East.
AN/TPS-77 and AN/TPS-78 Radar Systems$8282.79%September 2025: Taiwanese press report citing 2026 budget request says that all radar systems will be delivered by the end of 2028. TPS-77s scheduled to begin arriving in 2026; TPS-78s to begin arriving in 2027.
MQ-9B Unmanned Aircraft$6002.02%June 2026: Unknown number of drones in Taiwan undergoing assembly and pre-delivery flight testing b/n MND and manufacturer. Also included in MND force structure plan, drones and ground equipment expected to be shipped between July and September 2026.
HIMARS (Announced December 2022)$5201.75%June 2026: Included in MND force structure plan, 18 launchers expected “soon,” consistent with reporting from February 2026.
Javelin Missiles$3751.26%April 2026: MND issues procurement contract for โ€œanti-armor missiles,โ€ likely meaning Javelin or TOW-2B missiles, worth US$162.75 million, with estimated completion in September 2030.
Air-Launched Harpoon Missiles$3551.19%January 2023: Press report indicates that missiles will be delivered by 2030.
TOW Missiles$3531.19%April 2026: MND issues procurement contract for โ€œanti-armor missiles,โ€ likely meaning Javelin or TOW-2B missiles, worth US$162.75 million, with estimated completion in September 2030.
Field Information Communications System$2800.94%May 2025: Budget unfreezing report by MND indicates that testing of the system concluded in early 2025. The first batch of equipment is expected in the fourth quarter of 2025.
C4 Modernization$2650.89%No information since posting of Congressional notification.
Volcano Anti-Tank Mining System$1800.61%June 2026: Included in MND force structure plan, full order of 14 systems expected to ship “soon,” then be organized into “mobile interdiction teams” once in Taiwan, consistent with prior reporting.
Taiwan Advanced Tactical Data Link System Upgrade$750.25%August 2024: Taiwan’s E-Procurement System announced the award of a contract for the Link-16 system with completion date in 2026.
Switchblade 300 Loitering Missile System$600.20%September 2025: Taiwanese press reported details of delivery schedule: 66 drones already delivered to Military Police Command; 150 drones expected to be delivered to ROC Army by end of 2025, 469 drones by the end of 2026.
Munitions$2,3297.84%
AGM-84H SLAM-ER Missile$1,0083.39%December 2025: Taiwanese press report citing a publication by the LY’s budget office indicates a multi-year delay in finalizing details on cost and delivery schedule for AGM-84 missiles. Press report suggests that there is no finalized Letter of Offer and Acceptance (LOA) for this case, which would lay out a payment and delivery schedule.
F-16 Munitions$6192.08%April 2026: Raytheon awards contract for full-rate production of AMRAAM-ER missiles for FMS customers, including Taiwan.
Mk 48 Heavyweight Torpedoes (Announced June 2017)$2500.84%June 2026: MND reporting indicates deliveries of 28 in 2027 and 28 in 2028.
AGM-154C Joint Standoff Weapon$1860.62%December 2025: MND report to LY on arms sale delivery status reiterates that AGM-154C is one of three delayed arms sales cases.
Mk 48 Heavyweight Torpedoes (Announced May 2020)$1800.61%December 2025: MND report to LY on arms sale delivery status reiterates that Mk-48 is one of three delayed arms sales cases.
AIM-9X Block II Missiles$860.29%March 2024: SIPRI annual update indicates delivery is expected to occur by 2030.
Conclusion

June provided the clearest evidence so far in 2026 that several major arms sales are moving closer to delivery, even though the overall backlog remained unchanged at $29.72 billion. The apparent arrival of MQ-9Bs in Taiwan, continued F-16 flight testing, and new timelines for HIMARS, Harpoon missiles, reconnaissance pods, and Volcano systems suggest that Taiwan could receive a substantial package of capabilities before the end of the year. At the same time, the revised schedule for Mk 48 torpedoes demonstrates that delays continue to affect systems critical to Taiwanโ€™s longer-term force development. The coming months will show whether Juneโ€™s progress translates into completed deliveriesโ€”and whether Taiwan can absorb, integrate, and sustain several major systems arriving in close succession.

Taiwan Arms Sale Backlog, May 2026 Update

Abrams Delivered

Authors: Joe Oโ€™Connor & TSM Staff


May 2026 brought a major shift in arms sales to Taiwan. Taiwanโ€™s legislature agreed to a lower ceiling for the DPPโ€™s proposed special defense budget, and the Xi-Trump summit raised questions about the future of U.S. sales to Taipei. In May, Congress received no new Foreign Military Sales (FMS) notifications, and no existing sales were delivered. The total value of FMS cases notified to Congress but not yet delivered to Taiwan is still $29.72 billion.

Figure 1 shows how the backlog is divided among asymmetric weapons, traditional weapons, and munitions. Arms sales that are only partly delivered are marked in yellow-orange. Table 1 lists all arms sales in the backlog with the latest status updates. Partially delivered sales are shown in italics, while newly announced and fully delivered sales are marked with bold and underlining.

Special Budget Ceiling Authorized, Approved

On May 8, Taiwanโ€™s Legislative Yuan (LY) passed the โ€œSpecial Act for Safeguarding National Security and Strengthening Asymmetric Capabilities Procurement,โ€ after months of negotiations and delay. This act, which set only topline budget ceilings and regulated the budget process, authorized NT$780 billion (US$24.89 billion) for U.S. arms procurement, including NT$300 billion (US$9.57 billion) for FMS cases notified in December, including Paladin self-propelled howitzers, additional HIMARS launchers, and anti-tank missiles. On May 29, the LY approved initial special budget funding worth NT$8.81 billion (US$258.7 million), coming days before the payment deadline for HIMARS systems notified in December. This is notably about 60% of the Lai administrationโ€™s proposed NT$1.25 trillion (US$40 billion) special defense budget, originally announced in November 2025.

In response, President Lai Ching-te and other DPP officials expressed concerns that domestic production programs would not have continued funding, including Strong Bow ABM systems and โ€œSharp Kiteโ€ drones. Opposition lawmakers, including Kuomintang (KMT) chairwoman Cheng Li-wun and Taiwan Peopleโ€™s Party (TPP) chairman Huang Kuo-chang, celebrated the budget act, both expressing a desire to maintain oversight and not rubber-stamp the executive.

Trump-Xi Summit Sows Doubts About Sales to Taiwan

Mid-May was marked by a summit in Beijing between Presidents Trump and Xi, where the latter warned that the United States and China could find themselves in โ€œconfrontation or even conflictโ€ over Taipei. For purposes of arms sales, the summit yielded additional doubts about future U.S. policy towards Taiwan. Immediately after the summit, on May 15, Trump stated he โ€œwill make a determination over the next fairly short periodโ€ about arms sales to Taiwan, and dismissed the โ€œSix Assurances,โ€ a set of U.S. policies towards Taiwan developed in 1982. In an interview with Fox News several days later, Trump said that despite U.S. arms sales, the odds are against Taiwan in a conflict, and that he was pausing the latest U.S. sale to Taiwan to use as a โ€œvery good negotiating chipโ€ with China. This decision point on sales escalated in late May, when Trump stated he would speak with President Lai before deciding on the sales. On May 30, CBS reported that Trump decided not to speak with Lai, continuing a trend of no direct calls between U.S. and Taiwanese leaders since 1979.

In May, several senior Pentagon officials offered additional justification for a pause in arms sales to Taiwan. On May 21, Acting Secretary of the Navy Hung Cao told a Senate appropriations subcommittee that the U.S. has paused sales pending further talks with Beijing, including over the conflict in the Middle East. At the Shangri-La Conference on May 29, Secretary of Defense Pete Hegseth stated that the pause was not due to munitions stockpile concerns, stating that he would โ€œdecouple the twoโ€ [a pause in sales and Middle East conflict-related munitions shortages].

These inconsistencies are not good for Taipei and create uncertainty for the backlog. A reduction in sales would likely mean that the topline number of $29.72 billion would decrease over time as sales are completed; but a total pause in sales to Taiwan might be disastrous.

Case Updates and Related Contract Awards

There were few case updates in May, as much of the focus was on special defense budget spending and the Trump-Xi summit. In late May, Liberty Times reported that delivery of M109A7 Paladin self-propelled howitzers would not begin until 2030. Reportedly, this is tied to production capacity and delays in the queue. This sale of Paladins, notified in December 2025, consists of 60 M109A7s, 60 ammunition carriers, 13 recovery vehicles, and over 4,000 precision-guidance kits.
On May 12, the U.S. Navy awarded a $12 million contract for command, control, communications, and computers (C4) enterprise services for Taiwan, including extension options that would bring the total to $68 million. It is assessed that this contract award might apply to an FMS case for C4 modernization worth $265 million, notified in December 2024. 

Table 1
Itemized list of backlogged capabilities by weapons category, May 2026
Capability SoldDollar Value (In Millions)Share of total backlog, May 2026Current Status as of May 2026
Traditional$12,92743.50%
F-16C/D Block 70$8,00026.92%April 2026: Lockheed CFO Evan Scott notes in earnings call that production had “issues during the flight test” but they are “back on track” and deliveries of aircraft to Taiwan and Morocco would begin soon.
Paladin Self-Propelled Howitzer$4,03013.56%May 2026: Liberty Times reports that deliveries of Paladins are expected to start in 2030, due to U.S. production delays.
F-16 IRST Systems$5001.68%December 2025: US DoD awarded an undefinitized contract action to Lockheed Martin for targeting pods, including 55 IRST pods for Taiwan. Work is expected to complete by June 2031.
MS-110 Recce Pods$3671.24%February 2026: Three MS-110 pods expected to arrive by the end of 2026. This may fulfill the FMS case, but getting accurate, consistent numbers on MS-110 delivery has been challenging.
MK 75 76mm Gun Mounts$300.10%No information since posting of Congressional notification.
Asymmetric$14,46348.67%
HIMARS (Announced December 2025)$4,05013.63%April 2026: MND issues procurement contract for โ€œlong-range precision strike systems,โ€ likely meaning HIMARS, worth US$3.92 billion, with estimated completion in December 2032. Lockheed Martin also received a contract for full-rate production of launchers for U.S. and FMS customers, including Taiwan.
Harpoon Coastal Defense System$2,3707.97%March 2026: U.S. DSCA Director Michael Miller confirmed in a House hearing that Taiwan has priority for delivery of HCDS over Saudi Arabia.
National Advanced Surface-to-Surface Air Missile System (NASAMS)$1,1603.90%February 2026: Press reports citing MND sources repeated earlier reporting that Taiwan plans on purchasing 9 additional NASAMS systems and associated missiles. This appears to be one of the arms sales cases being held up by special procurement budget deadlock in the LY.
ALTIUS (Announced December 2025)$1,1003.70%January 2026: MND reported that it would purchase 1,554 ALTIUS-700M loitering munitions and 478 ALTIUS-600M ISR drones. The FMS notification did not specify the number of drones being purchased.
Tactical Mission Network$1,0103.40%January 2026: LY votes to move a special procurement budget proposed by the TPP to committee for consideration. The bill would not fund the Tactical Mission Network, but would fund almost all other FMS cases notified to Congress in December 2025.
PAC-3 MSE Interceptors$8822.97%March 2026: MND officials stated that ongoing delivery of 102 MSE missiles should not be affected by conflict in the Middle East.
AN/TPS-77 and AN/TPS-78 Radar Systems$8282.79%September 2025: Taiwanese press report citing 2026 budget request says that all radar systems will be delivered by the end of 2028. TPS-77s scheduled to begin arriving in 2026; TPS-78s to begin arriving in 2027.
MQ-9B Unmanned Aircraft$6002.02%March 2026: Taiwanese officials attended a โ€œhandoverโ€ ceremony in the U.S. for two of the expected four drones, clarifying that they expect to remain for further testing. LY testimony from MND officials also clarified that delivery is expected by the third quarter of 2026 and should not be delayed by ongoing conflict in the Middle East.
HIMARS (Announced December 2022)$5201.75%February 2026: Press reports citing MND sources indicate that 18 launchers, 20 ATACMS, and 864 GMLRS are expected to arrive before the fourth quarter of 2026. This is consistent with previously reported delivery timelines.
Javelin Missiles$3751.26%April 2026: MND issues procurement contract for โ€œanti-armor missiles,โ€ likely meaning Javelin or TOW-2B missiles, worth US$162.75 million, with estimated completion in September 2030.
Air-Launched Harpoon Missiles$3551.19%January 2023: Press report indicates that missiles will be delivered by 2030.
TOW Missiles$3531.19%April 2026: MND issues procurement contract for โ€œanti-armor missiles,โ€ likely meaning Javelin or TOW-2B missiles, worth US$162.75 million, with estimated completion in September 2030.
Field Information Communications System$2800.94%May 2025: Budget unfreezing report by MND indicates that testing of the system concluded in early 2025. The first batch of equipment is expected in the fourth quarter of 2025.
C4 Modernization$2650.89%No information since posting of Congressional notification.
Volcano Anti-Tank Mining System$1800.61%February 2026: Press reports citing MND sources indicate delivery of 14 Volcano systems will occur “soon.” This is consistent with previously reported delivery timelines.
Taiwan Advanced Tactical Data Link System Upgrade$750.25%August 2024: Taiwan’s E-Procurement System announced the award of a contract for the Link-16 system with completion date in 2026.
Switchblade 300 Loitering Missile System$600.20%September 2025: Taiwanese press reported details of delivery schedule: 66 drones already delivered to Military Police Command; 150 drones expected to be delivered to ROC Army by end of 2025, 469 drones by the end of 2026.
Munitions$2,3297.84%
AGM-84H SLAM-ER Missile$1,0083.39%December 2025: Taiwanese press report citing a publication by the LY’s budget office indicates a multi-year delay in finalizing details on cost and delivery schedule for AGM-84 missiles. Press report suggests that there is no finalized Letter of Offer and Acceptance (LOA) for this case, which would lay out a payment and delivery schedule.
F-16 Munitions$6192.08%April 2026: Raytheon awards contract for full-rate production of AMRAAM-ER missiles for FMS customers, including Taiwan.
Mk 48 Heavyweight Torpedoes (Announced June 2017)$2500.84%December 2025: MND report to LY on arms sale delivery status reiterates that Mk-48 is one of three delayed arms sales cases.
AGM-154C Joint Standoff Weapon$1860.62%December 2025: MND report to LY on arms sale delivery status reiterates that AGM-154C is one of three delayed arms sales cases.
Mk 48 Heavyweight Torpedoes (Announced May 2020)$1800.61%December 2025: MND report to LY on arms sale delivery status reiterates that Mk-48 is one of three delayed arms sales cases.
AIM-9X Block II Missiles$860.29%March 2024: SIPRI annual update indicates delivery is expected to occur by 2030.
Conclusion

Taiwanโ€™s arms sale backlog remained steady at $29.72 billion through the end of May 2026. The Legislative Yuanโ€™s passage of a reduced special defense budget and initial funding for Decemberโ€™s FMS cases are positive developments, but additional appropriations will be necessary to keep these purchases moving forward. Meanwhile, the reported Paladin delivery delay and the Trump administrationโ€™s inconsistent statements on future sales show that both production capacity and political considerations continue to affect the backlog. The coming months will indicate whether Taiwan can secure the remaining funding and whether Washington will resume notifying Congress of new arms sales.

Taiwan Arms Sale Backlog,ย Aprilย 2026 Updateย 

Abrams Delivered

Authors: Joe Oโ€™Connor, Eric Gomez, Shikhar Chaturvedi, Danielle Kremer, and Wyeth Lindberg 


As of the end of April 2026, Taiwanโ€™s legislature had failed to reach an agreement on a special defense budget to fund U.S. arms sales, continuing to place several high-value sales in jeopardy. (As of the time of publication, this has changed. Discussion about the recent approval of a budget by the Legislative Yuan will be discussed in the May update).  

April had exceedingly good news for the backlog, however, as a third and final batch of M1A2T Abrams main battle tanks arrived in Taipei at the end of the month. With this delivery, the Abrams FMS case is completed, and the backlogโ€™s value is reduced by US$2 billion. This brings the total value of the backlog to $29.72 billion. 

Figure 1 illustrates the breakdown of the backlog between asymmetric weapons, traditional weapons, and munitions; arms sales that have been partially but not fully delivered are indicated with a yellow-orange color. Table 1 provides an itemized list of all arms sales in the backlog, including the most up-to-date information on their status. Arms sales that have been partially but not fully delivered are indicated with italics. Newly announced and fully delivered arms sales are indicated with bolding and underlining, respectively. 

 
Table 1
Itemized list of backlogged capabilities by weapons category, April
Capability SoldDollar Value (In Millions)Share of total backlog, April 2026Current Status as of April 2026
Traditional$12,92743.50%
F-16C/D Block 70$8,00026.92%April 2026: Lockheed CFO Evan Scott notes in earnings call that production had “issues during the flight test” but they are “back on track” and deliveries of aircraft to Taiwan and Morocco would begin soon.
Paladin Self-Propelled Howitzer$4,03013.56%April 2026: MND issues procurement contract for “self-propelled artillery,” likely meaning Paladins, worth US$2.35 billion, with estimated completion in December 2034.
M1A2T Abrams Tanks$2,000N/AApril 2026: MND confirms delivery of last 28 tanks at Port of Taipei. All 108 Abrams tanks have now been delivered to Taiwan.
F-16 IRST Systems$5001.68%December 2025: US DoD awarded an undefinitized contract action to Lockheed Martin for targeting pods, including 55 IRST pods for Taiwan. Work is expected to complete by June 2031.
MS-110 Recce Pods$3671.24%February 2026: Three MS-110 pods expected to arrive by the end of 2026. This may fulfill the FMS case, but getting accurate, consistent numbers on MS-110 delivery has been challenging.
MK 75 76mm Gun Mounts$300.10%No information since posting of Congressional notification.
Asymmetric$14,46348.67%
HIMARS (Announced December 2025)$4,05013.63%April 2026: MND issues procurement contract for โ€œlong-range precision strike systems,โ€ likely meaning HIMARS, worth US$3.92 billion, with estimated completion in December 2032. Lockheed Martin also received a contract for full-rate production of launchers for U.S. and FMS customers, including Taiwan.
Harpoon Coastal Defense System$2,3707.97%March 2026: U.S. DSCA Director Michael Miller confirmed in a House hearing that Taiwan has priority for delivery of HCDS over Saudi Arabia.
National Advanced Surface-to-Surface Air Missile System (NASAMS)$1,1603.90%February 2026: Press reports citing MND sources repeated earlier reporting that Taiwan plans on purchasing 9 additional NASAMS systems and associated missiles. This appears to be one of the arms sales cases being held up by special procurement budget deadlock in the LY.
ALTIUS (Announced December 2025)$1,1003.70%January 2026: MND reported that it would purchase 1,554 ALTIUS-700M loitering munitions and 478 ALTIUS-600M ISR drones. The FMS notification did not specify the number of drones being purchased.
Tactical Mission Network$1,0103.40%January 2026: LY votes to move a special procurement budget proposed by the TPP to committee for consideration. The bill would not fund the Tactical Mission Network, but would fund almost all other FMS cases notified to Congress in December 2025.
PAC-3 MSE Interceptors$8822.97%March 2026: MND officials stated that ongoing delivery of 102 MSE missiles should not be affected by conflict in the Middle East.
AN/TPS-77 and AN/TPS-78 Radar Systems$8282.79%September 2025: Taiwanese press report citing 2026 budget request says that all radar systems will be delivered by the end of 2028. TPS-77s scheduled to begin arriving in 2026; TPS-78s to begin arriving in 2027.
MQ-9B Unmanned Aircraft$6002.02%March 2026: Taiwanese officials attended a โ€œhandoverโ€ ceremony in the U.S. for two of the expected four drones, clarifying that they expect to remain for further testing. LY testimony from MND officials also clarified that delivery is expected by the third quarter of 2026 and should not be delayed by ongoing conflict in the Middle East.
HIMARS (Announced December 2022)$5201.75%February 2026: Press reports citing MND sources indicate that 18 launchers, 20 ATACMS, and 864 GMLRS are expected to arrive before the fourth quarter of 2026. This is consistent with previously reported delivery timelines.
Javelin Missiles$3751.26%April 2026: MND issues procurement contract for โ€œanti-armor missiles,โ€ likely meaning Javelin or TOW-2B missiles, worth US$162.75 million, with estimated completion in September 2030.
Air-Launched Harpoon Missiles$3551.19%January 2023: Press report indicates that missiles will be delivered by 2030.
TOW Missiles$3531.19%April 2026: MND issues procurement contract for โ€œanti-armor missiles,โ€ likely meaning Javelin or TOW-2B missiles, worth US$162.75 million, with estimated completion in September 2030.
Field Information Communications System$2800.94%May 2025: Budget unfreezing report by MND indicates that testing of the system concluded in early 2025. The first batch of equipment is expected in the fourth quarter of 2025.
C4 Modernization$2650.89%No information since posting of Congressional notification.
Volcano Anti-Tank Mining System$1800.61%February 2026: Press reports citing MND sources indicate delivery of 14 Volcano systems will occur “soon.” This is consistent with previously reported delivery timelines.
Taiwan Advanced Tactical Data Link System Upgrade$750.25%August 2024: Taiwan’s E-Procurement System announced the award of a contract for the Link-16 system with completion date in 2026.
Switchblade 300 Loitering Missile System$600.20%September 2025: Taiwanese press reported details of delivery schedule: 66 drones already delivered to Military Police Command; 150 drones expected to be delivered to ROC Army by end of 2025, 469 drones by the end of 2026.
Munitions$2,3297.84%
AGM-84H SLAM-ER Missile$1,0083.39%December 2025: Taiwanese press report citing a publication by the LY’s budget office indicates a multi-year delay in finalizing details on cost and delivery schedule for AGM-84 missiles. Press report suggests that there is no finalized Letter of Offer and Acceptance (LOA) for this case, which would lay out a payment and delivery schedule.
F-16 Munitions$6192.08%April 2026: Raytheon awards contract for full-rate production of AMRAAM-ER missiles for FMS customers, including Taiwan.
Mk 48 Heavyweight Torpedoes (Announced June 2017)$2500.84%December 2025: MND report to LY on arms sale delivery status reiterates that Mk-48 is one of three delayed arms sales cases.
AGM-154C Joint Standoff Weapon$1860.62%December 2025: MND report to LY on arms sale delivery status reiterates that AGM-154C is one of three delayed arms sales cases.
Mk 48 Heavyweight Torpedoes (Announced May 2020)$1800.61%December 2025: MND report to LY on arms sale delivery status reiterates that Mk-48 is one of three delayed arms sales cases.
AIM-9X Block II Missiles$860.29%March 2024: SIPRI annual update indicates delivery is expected to occur by 2030.
Last Batch of Abrams Delivered  

On April 27, Liberty Times reported that the third and final batch of M1A2T Abrams tanks purchased from the United States have arrived at Taipei Port. Representing 6.3% of last monthโ€™s US$31.72 billion backlog topline. The Abrams FMS case was originally notified to Congress in July 2019. The first batch of 38 tanks arrived in December 2024, with a second batch of 42 arriving July 2025. Now that all tanks are present, they will participate in transition training, quality evaluations, and combat readiness drills, including shooting and maneuver drills. If training progresses well, the tanks may be ready for service by the end of this year.

Special Budget Updates in April 

Aprilโ€™s special budget developments began with further delay, owing to Kuomintang (KMT) chair Cheng Li-wun’s visit to China early in the month. Because of the visit, KMT legislators on April 2 requested Democratic Progressive Party (DPP) convener, Chen Kuan-ting, to delay negotiations until mid-April. Chen refused, resulting in a scheduled hearing on April 9 where KMT members did not appear, leading to widespread condemnation by DPP officials, accusing them of obstruction. An additional hearing on April 15, chaired by LY Speaker Han Kuo-yu, also resulted in no consensus from all three parties. 
Around the middle of the month, stakeholders began to weigh in on the ongoing negotiations, including President Lai Ching-te, who urged the need for โ€œconstant preparednessโ€ at a military inspection in Kaohsiung. Four U.S. Senators, including Senate Foreign Relations Committee Ranking Member Jeanne Shaheen (D-NH), sent a letter to LY officials urging them to โ€œapprove a supplementary defense budgetโ€ that addresses ongoing U.S. sales, as well as โ€œspeedier domestic production.โ€  
In an April 20  closed-door hearing of the LYโ€™s Foreign Affairs and National Defense Committee, Minister of National Defense Wellington Koo submitted a new, partially redacted version of the DPPโ€™s NT$1.25 trillion (US$40 billion) proposal. In his testimony, Koo also maintained the need for a larger budget to plan around โ€œoperational needs.โ€ 
Rifts within the KMT more overtly emerged in April, including a caucus meeting on April 29 which indicated large divisions, between members who supported a budget of NT$800 billion (US$25 billion) over the original KMT proposal of NT$380 billion (US$12 billion). That same caucus meeting resulted in the party’s vice chairman, Chi Lin-lien threatening to expel LY Speaker Han Kuo-yu from the party for his support of NT$800 billion, an accusation that was quickly dispelled by KMT chair Cheng. However, discussions between the KMT and Taiwan Peopleโ€™s Party (TPP), their coalition partner, indicated that both would agree on a unified proposal of NT$800 billion.

MND Issues Seven Major Contracts for Backlogged Items 

On April 21-22, the Taiwanese Ministry of National Defense (MND) issued awards for seven major procurement contracts to the American Institute in Taiwan (AIT), which indicates they will be fulfilled by a U.S. defense contractor. A summary of the contracts is listed below: 

  • โ€œLong-range precision strike systems,โ€ for the Army Command, worth US$3.92 billion (NT$122.95 billion), with an estimated completion date in December 2032. This is meant to be High Mobility Artillery Rocket Systems (HIMARS) launchers and munitions notified to Congress in December 2025. 
  • โ€œSelf-propelled artillery,โ€ for the Army Command, worth US$2.35 billion (NT$73.71 billion), with an estimated completion date of December 2034. This is meant to be M109A7 Paladin self-propelled howitzers and munitions.
  • โ€œAnti-armor missiles,โ€ for the Naval Command, worth US$162.75 million (NT$5.10 billion), with an estimated completion date of September 2030. This might be Javelin or TOW-2B anti-armor missiles, meant for the ROC Marine Corps.
  • โ€œOther support services,โ€ for the Air Force Command, worth US$18.26 million (NT$572.60 million). 
  • โ€œCo-production of large-caliber ammunition,โ€ for the Armaments Bureau, worth US$29 million (NT$909.6 billion). It is assumed this means 155-mm artillery shells, along with other munitions. 
  • โ€œIntegrated air defense services,โ€ for the General Staff, worth US$730,000 (NT$22.90 million). This is likely for Taiwanโ€™s proposed โ€œT-Domeโ€ air and missile defense system concept. 


These seven contracts together amount to US$6.65 billion (NT$205.6 billion) in military procurement and defense-related services. Three of these contracts are explicitly for equipment notified in December (HIMARS, Paladin, and TOW / Javelin) as part of a larger US$11 billion package.  

F-16 Block 70 and Contract Updates of Note 

Lockheed Martinโ€™s April earnings call provided additional detail on delays affecting Taiwanโ€™s F-16C/D Block 70 case. On April 23, Lockheed Martin CFO Evan Scott told shareholders that the Taiwan and Morocco F-16 production run had encountered โ€œissues during the flight test,โ€ delaying deliveries. Scott said the program is now โ€œback on trackโ€ after a successful flight test and that Lockheed planned to begin deliveries of the first aircraft as soon as that week. As previously noted in TSMโ€™s Weekly Arms Update, it remains unclear whether Taiwan or Morocco will receive the first aircraft. This also follows TSMโ€™s March Backlog update, which noted that Taiwanese officials attended an Acceptance Check Flight in Greenville, South Carolina, and that Minister of National Defense Wellington Koo said the first F-16s could arrive in Taiwan as early as September 2026. The F-16 case remains the largest single item in the backlog, valued at US$8 billion (NT$253.2 billion). 
Two U.S. contract award announcements also involved Taiwan as an FMS customer among other countries. On April 15, Raytheon received a $234.8 million (NT$7.4 billion) undefinitized contract action to transition Advanced Medium-Range Air-to-Air Missiles-Extended Range (AMRAAM-ER) into full-rate production, with Taiwan listed among the FMS customers. Then, on April 29, Lockheed Martin received a $1.13 billion (NT$3.58 billion) undefinitized contract action for full-rate production of M142 High Mobility Artillery Rocket Systems (HIMARS) launchers and supporting requirements for the U.S. Army, Marine Corps, and FMS customers, including Taiwan. These contract award announcements do not change the delivery status of in the arms backlog, but, in the case of HIMARS, it shows forward progress by the United States despite the political deadlock in the Legislative Yuan over the special procurement budget.  

Conclusion 

The delivery of the final Abrams tanks has lowered the total backlog, and the MNDโ€™s April contract awards indicate that several major cases are moving forward. However, continued progress depends on Taiwanโ€™s ability to match deliveries and contracts with political consensus, funding, training, and integration. The special budget debate remains critical: without a stable legislative path to finance current and future purchases, even significant deliveries will only partially address the gap between approved arms sales and operational needs. Developments in Mayโ€™s budget will show whether Aprilโ€™s progress marks the beginning of broader acceleration or remains a limited improvement within a significant backlog. 

Taiwan Arms Sale Backlog,ย Marchย 2026 Updateย 

Abrams and ALTIUS Delivered, But Further Delays Emerge

Authors: Joe Oโ€™Connor, Eric Gomez, Shikhar Chaturvedi, Danielle Kremer, and Wyeth Lindberg 


Taiwanโ€™s legislature failed to reach an agreement on a special procurement budget to fund U.S. arms sales in March, which is already delaying Foreign Military Sales (FMS) cases worth over $10 billion.  

But March had good news for the U.S. arms sale backlog as well. A June 2024 FMS case for ALTIUS drones was fully delivered, reducing the backlogโ€™s dollar value by $300 million. The final tranche of Abrams tanks is also on its way to Taiwan by ship. Once these tanks arrive the backlog will come down by $2 billion, but we were not able to verify their delivery before the end of March so that FMS case is still coded as delivery in progress for this month. No new FMS cases were notified to Congress this month. 

The delivery of ALTIUS drones brings the backlogโ€™s total value down slightly to $31.72 billion.  

Figure 1 illustrates the breakdown of the backlog between asymmetric weapons, traditional weapons, and munitions. Table 1 provides an itemized list of all arms sales in the backlog, including the most up-to-date information on their status. In that table, arms sales that have been partially but not fully delivered are indicated in italics. New and completed arms sales are indicated with bolding and underlining.  

Special Budget Updates in March 

On March 5, the Kuomintang (KMT) released their proposal for US$12.02 billion (NT$380 billion) in spending, to fund only the arms approved in December 2025. This proposal required that Letters of Offer and Acceptance (LOAs) be approved before funds are appropriated, instead of having funds in advance. The KMTโ€™s proposal also required that funds for future arms sales from the US be approved as a second bill, instead of the Lai administration or Taiwan Peopleโ€™s Party (TPP) proposals, which allocate funds for future arms purchases. 

Following its release, Minister of National Defense Wellington Koo and statements carried by the Military News Agency (MNA) pushed back against the proposal, arguing that its sunset provision of December 2028 is incompatible with current delivery timelines and unrealistic. The MND also clarified in a statement that three sales announced in December, including the Taiwan Tactical Network, as well as AH-1W spare parts and Harpoon missile refurbishment, were not included within the administrationโ€™s NT$1.25 trillion special budget request, instead being folded under annual defense spending. 

Table 1
Itemized list of backlogged capabilities by weapons category, March 2026
Capability SoldDollar Value (In Millions)Share of total backlog, March 2026Current Status as of March 2026
Traditional$14,92747.06%
F-16C/D Block 70$8,00025.22%March 2026: Taiwanese officials attended an Acceptance Check Flight in the U.S. for the first F-16 airframe. Minister Koo also stated to press that the first F-16 could arrive as early as September 2026.
Paladin Self-Propelled Howitzer$4,03012.71%March 2026: MND officials warned that Letter of Offer and Acceptance for Paladins, as well as three other sales, would expire at end of month if not signed. LY agreed to allow signature of LOAs before special defense budget is approved.
M1A2T Abrams Tanks$2,0006.31%March 2026: MND officials stated that the final batch of 28 Abrams are โ€œat seaโ€ enroute to Taiwan. Further statements indicated delivery either at the end of March or in April. As of the end of March, TSM cannot independently verify delivery.
F-16 IRST Systems$5001.58%December 2025: US DoD awarded an undefinitized contract action to Lockheed Martin for targeting pods, including 55 IRST pods for Taiwan. Work is expected to complete by June 2031.
MS-110 Recce Pods$3671.16%February 2026: Three MS-110 pods expected to arrive by the end of 2026. This may fulfill the FMS case, but getting accurate, consistent numbers on MS-110 delivery has been challenging.
MK 75 76mm Gun Mounts$300.09%No information since posting of Congressional notification.
Asymmetric$14,46345.60%
HIMARS (Announced December 2025)$4,05012.77%March 2026: MND officials warned that Letter of Offer and Acceptance for HIMARS, as well as three other sales, would expire at end of month if not signed. LY agreed to allow signature of LOAs before special defense budget is approved. MND officials also warned that initial payment for HIMARS would be due, but agreements with U.S. officials resulted in an extension.
Harpoon Coastal Defense System$2,3707.47%March 2026: U.S. DSCA Director Michael Miller confirmed in a House hearing that Taiwan has priority for delivery of HCDS over Saudi Arabia.
National Advanced Surface-to-Surface Air Missile System (NASAMS)$1,1603.66%February 2026: Press reports citing MND sources repeated earlier reporting that Taiwan plans on purchasing 9 additional NASAMS systems and associated missiles. This appears to be one of the arms sales cases being held up by special procurement budget deadlock in the LY.
ALTIUS (Announced December 2025)$1,1003.47%January 2026: MND reported that it would purchase 1,554 ALTIUS-700M loitering munitions and 478 ALTIUS-600M ISR drones. The FMS notification did not specify the number of drones being purchased.
Tactical Mission Network$1,0103.18%January 2026: LY votes to move a special procurement budget proposed by the TPP to committee for consideration. The bill would not fund the Tactical Mission Network, but would fund almost all other FMS cases notified to Congress in December 2025.
PAC-3 MSE Interceptors$8822.78%March 2026: MND officials stated that ongoing delivery of 102 MSE missiles should not be affected by conflict in the Middle East.
AN/TPS-77 and AN/TPS-78 Radar Systems$8282.61%September 2025: Taiwanese press report citing 2026 budget request says that all radar systems will be delivered by the end of 2028. TPS-77s scheduled to begin arriving in 2026; TPS-78s to begin arriving in 2027.
MQ-9B Unmanned Aircraft$6001.89%March 2026: Taiwanese officials attended a โ€œhandoverโ€ ceremony in the U.S. for two of the expected four drones, clarifying that they expect to remain for further testing. LY testimony from MND officials also clarified that delivery is expected by the third quarter of 2026 and should not be delayed by ongoing conflict in the Middle East.
HIMARS (Announced December 2022)$5201.64%February 2026: Press reports citing MND sources indicate that 18 launchers, 20 ATACMS, and 864 GMLRS are expected to arrive before the fourth quarter of 2026. This is consistent with previously reported delivery timelines.
Javelin Missiles$3751.18%March 2026: MND officials warned that Letter of Offer and Acceptance for Javelins, as well as three other sales, would expire at end of month if not signed. LY agreed to allow signature of LOAs before special defense budget is approved.
Air-Launched Harpoon Missiles$3551.12%January 2023: Press report indicates that missiles will be delivered by 2030.
TOW Missiles$3531.11%March 2026: MND officials warned that Letter of Offer and Acceptance for TOWs, as well as three other sales, would expire at end of month if not signed. LY agrees to allow signature of LOAs before special defense budget is approved.
ALTIUS (Announced June 2024)$3000.90%March 2026: MND confirms receipt of all 291 ALTIUS-600M UAVs.
Field Information Communications System$2800.88%May 2025: Budget unfreezing report by MND indicates that testing of the system concluded in early 2025. The first batch of equipment is expected in the fourth quarter of 2025.
C4 Modernization$2650.84%No information since posting of Congressional notification.
Volcano Anti-Tank Mining System$1800.57%February 2026: Press reports citing MND sources indicate delivery of 14 Volcano systems will occur “soon.” This is consistent with previously reported delivery timelines.
Taiwan Advanced Tactical Data Link System Upgrade$750.24%August 2024: Taiwan’s E-Procurement System announced the award of a contract for the Link-16 system with completion date in 2026.
Switchblade 300 Loitering Missile System$600.19%September 2025: Taiwanese press reported details of delivery schedule: 66 drones already delivered to Military Police Command; 150 drones expected to be delivered to ROC Army by end of 2025, 469 drones by the end of 2026.
Munitions$2,3297.34%
AGM-84H SLAM-ER Missile$1,0083.18%December 2025: Taiwanese press report citing a publication by the LY’s budget office indicates a multi-year delay in finalizing details on cost and delivery schedule for AGM-84 missiles. Press report suggests that there is no finalized Letter of Offer and Acceptance (LOA) for this case, which would lay out a payment and delivery schedule.
F-16 Munitions$6191.95%July 2025: US DoD awarded Raytheon a $3.5 billion contract for Lots 39 and 40 of AMRAAM production, to be completed in 2031. Taiwan is one of many FMS customers and specific delivery timeline is not clear.
Mk 48 Heavyweight Torpedoes (Announced June 2017)$2500.79%December 2025: MND report to LY on arms sale delivery status reiterates that Mk-48 is one of three delayed arms sales cases.
AGM-154C Joint Standoff Weapon$1860.58%December 2025: MND report to LY on arms sale delivery status reiterates that AGM-154C is one of three delayed arms sales cases.
Mk 48 Heavyweight Torpedoes (Announced May 2020)$1800.57%December 2025: MND report to LY on arms sale delivery status reiterates that Mk-48 is one of three delayed arms sales cases.
AIM-9X Block II Missiles$860.27%March 2024: SIPRI annual update indicates delivery is expected to occur by 2030.

On March 25, the Legislative Yuanโ€™s Foreign Affairs and National Defense Committee began a two-day markup period of the three budget proposals, aiming to combine them into one bill. Committee members reached consensus on several provisions, including those relating to procurement planning, taken from the KMT proposal, as well as legal authorities, but crucially failed to reach consensus on provisions relating to the topline budget amount and specific procurement items. In the hearing, opposition legislators questioned the governmentโ€™s proposed spending categories, concerned that they were vague or classified. By law, the special budget entered a โ€œfreezeโ€ to allow for further negotiation, which is expected to go into April. Discussed below, these repeated delays and lack of consensus, while somewhat productive in challenging Lai administration policy, have also had negative knock-on effects, resulting in delayed or extended payments for several arms sales. 

March also featured several statements from Taiwanese officials on the status of the special budget. On March 8, President Lai, speaking at a temple in New Taipei, stated his administrationโ€™s budget was reasonable and compared it to a security system against a โ€œbad neighbor.โ€ On March 28, Premier Cho Jung-tai urged opposition parties to perceive the need for national defense and the nationโ€™s requirements, after a markup hearing in which General Huang Wen-chi, head of the MNDโ€™s Strategic Planning Department, was visibly upset. The same day, Vice President Hsiao Bi-khim echoed the same sentiments, speaking at the 2026 Taiwan Civil Defense Annual Conference and noting that the administrationโ€™s budget seeks to improve โ€œwhole-of-society resilience.โ€ 

American officials also weighed in. On March 9, a State Department spokesperson stated that Washington โ€œencourage[s] all parties in Taiwanโ€™s legislature to work through political differences and quickly pass a special defense budget,โ€ specifically addressing whether the United States would support a KMT proposal. On March 26, Director of the American Institute in Taiwan, Raymond Greene, also urged the LY to pass a budget, calling U.S. support for it โ€œrock solid.โ€ 

December Cases Face LOA and Payment Extensions, Possible Delays  

Taipei spent most of March trying to prevent a procedural problem from becoming a delivery problem. In early February, the Ministry of National Defense warned that the LOAs for TOW anti-armor missiles, Javelin anti-armor missiles, and M109A7 self-propelled howitzers would expire on March 15 unless the Legislative Yuan acted. Following this, the LY moved on March 12โ€“13 to authorize the Executive Yuan to sign four U.S. LOAs, adding HIMARS to the original three cases.  While a crucial step, as it prevented the deals from stalling at the signature stage, it did not fully solve the larger problem. In the FMS process, an LOA must be signed and an initial payment made before the U.S. procurement agency can enter into an agreement with the defense industry to build the weapons. Clearing the LOA signature step is a move in the right direction, but Taiwanโ€™s special procurement budget impasse means that it cannot make an initial payment, which means delays in finalizing production contracts.   

On March 26, Liberty Times reported that the initial payment deadline for HIMARS was approaching and that U.S. officials had indicated there was little room for delay, with Taiwanese officials warning that missing the current deadline could push negotiations for a new LOA back to the end of the year. Four days later, CNA reported that the United States had agreed to extend the HIMARS first-payment deadline with a revised timeline tied to the U.S. Department of Defenseโ€™s contract negotiations with Lockheed Martin, the systemโ€™s manufacturer. Taiwan is still seeking similar flexibility for the TOW, Javelin, and M109A7 cases.  

Updates to Abrams, ALTIUS Deliveries 

On March 10, MND officials reported that the final tranche of 28 M1A2T Abrams tanks is โ€œat sea,โ€ en route to Taiwan, however we were unable to verify delivery of the tanks before the end of March.. 80 of the 108 tanks have already arrived, including 38 delivered in December 2024 and 42 delivered in July 2025. Once delivered, this tranche will mark the last of 108 Abrams that Taiwan began procuring in July 2019. From a procurement perspective, the Abrams case is a useful execution benchmark inside the broader U.S.โ€“Taiwan pipeline. Taiwan Security Monitorโ€™s backlog tracker has identified Abrams as one of the smoother Foreign Military Sales deliveries. Final delivery of the Abrams would reduce the backlog by $2 billion, a sizable decrease.  

As of March 18, the Taiwanese military has officially received all ALTIUS-600M UAVs purchased from the United States and defense contractor Anduril. Announced on June 18, 2024, the first batch of ALTIUS-600M drones was delivered to Taiwan on August 4, 2025, a turn-around time between approval and initial delivery of less than 14 months. With this last delivery, the Taiwanese military now has up to 291 ALTIUS systems, costing approximately NT$9.6 billion (US$300 million). A second sale, announced in December, of 1,554 ALTIUS 700M and 478 ALTIUS 600M ISR drones, is currently in progress, and is also expected to be completed quickly. 

F-16 Block 70 and MQ-9B Production Updates 

As of March 21, the first Taiwanese F-16 Block 70 has completed its Acceptance Check Flight at Lockheed Martin facilities in Greenville, South Carolina. These tests were attended by several Taiwanese officials, including Deputy Minister of National Defense Hsu Szu-chien, Deputy Air Force Chief of Staff General Tian Zhongyi, and the Taiwanese Representative to the United States, Alexander Yui. An MND press release after the visit stated that this success means Lockheed will begin its deliveries to Taiwan. On the same day, the MND also confirmed that several Taiwanese officials attended a handover ceremony in the United States for two of the four MQ-9B SeaGuardian maritime surveillance drones purchased for NT$21.7 billion (US$674.02 million). However, the MND clarified that the two drones would stay in the United States for continued testing, with delivery to Taiwan expected in the third quarter of this year. 

Minister of National Defense Wellington Koo also stated in a recent press conference that the first two MQ-9B SeaGuardians are expected to be delivered by the third quarter of the year and that the first F-16 Block 70 could arrive as early as September 2026. He has also clarified that the United States’ ongoing conflict in the Middle East has no effect on delivery timelines to Taiwan. 

Conclusion

Taken together, Marchโ€™s developments show a backlog that is still slowly moving in the right direction, but with growing signs that Taiwanโ€™s main bottleneck is no longer only United Statesโ€™  production capacity. The completion of ALTIUS deliveries, the near-finish of the Abrams case, and visible progress on the F-16 Block 70 and MQ-9B programs are welcome developments. At the same time, repeated delays in passing a special defense budget, uncertainty over LOA follow-through and initial payments, and the need to seek deadline extensions from Washington indicate that domestic political and procedural friction in Taiwan are increasingly shaping the pace of FMS execution.  

Errata: Percentages in Table 1 inaccurately reflected sale value and have been appropriately updated.

Taiwan Arms Sale Backlog, February 2026 Update

Special Budget Complications Continue

Authors: Joseph Oโ€™Connor, Eric Gomez, & Shikhar Chaturvedi


Political gridlock over the Lai administrationโ€™s special procurement budget continued in February 2026, leading to concerns about recently announced U.S. arms sales to Taiwan. No new Foreign Military Sales (FMS) cases were notified to Congress, and no existing sales were delivered in February. The total value of FMS cases notified to Congress but not delivered to Taiwan remains $32 billion.

Eagle-eyed readers will notice that there is a change in Figure 1. Arms sales cases are fully removed from our dataset once final delivery occurs, but we do not reduce the dollar value of the backlog for partial deliveries. We have explained our thinking in other articles.

We indicate partially delivered arms sales through color coding in our data visualizations, with the yellow-orange color representing cases that are partially delivered to the best of our knowledge. Previously, we have only done this for arms sales valued at $1 billion or more because these were the most militarily significant sales and because, given the quantities and types of capabilities involved, they tended to be the easiest to track.

However, we realize that a $1 billion threshold has its own problems. We have therefore decided to adjust our methodology for data visualizations, and from now on, any arms sale that we can verify as partially delivered will be visually indicated with the yellow-orange color. The dollar value of the backlog will only be reduced when a sale is fully delivered, but we think this new approach represents a reasonable way to show in-progress deliveries.

This methodology change moves five arms sales cases worth $1.89 billion into the partially delivered category. Combined with the two cases above, the $1 billion threshold that we were already tracking as partially deliveredโ€”M1A2T Abrams tanks and Harpoon Coastal Defense Cruise Missile systemsโ€”there are seven arms sales cases worth $6.26 billion that are partially delivered, just shy of 20 percent of the backlogโ€™s total dollar value.  

Special Budget Updates in February

Ongoing deliberations in the Legislative Yuan (LY) relating to a special defense budget slowed down in February, as the LY recessed for the Lunar New Year holiday. Prior to recess, the legislature voted to advance a proposal made by the opposition Taiwan Peopleโ€™s Party (TPP) to committee review, leaving the Lai administrationโ€™s NT$1.25 trillion (US$40 billion) proposal in limbo. During the recess, 37 U.S. senators and representatives, including senior members of the House and Senate foreign affairs committees and from both parties in Congress, sent a letter to LY Speaker Han Kuo-yu and party caucus leaders, expressing concern about โ€œongoing deliberations in the Legislative Yuan to only partially fund a supplemental budget request.โ€ Han, responding on February 16, stated that the budget would be one of the โ€œvery firstโ€ items to be debated, and upon re-convening on February 24, the LY voted to advance the governmentโ€™s proposal, ending the month with both proposals under review by the Foreign Affairs and National Defense Committee.

The differences between the competing proposals largely center on flexibility and holistic spending, as opposed to narrower and targeted procurements of established systems, as discussed in detail in our recent article comparing the two proposals. On the sidelines, the Kuomintang (KMT), the third and largest major party in the LY, announced in late February that they would be releasing their own special budget proposal, which they did in early March. As of the end of February, the proposal had ranged from NT$350 billion (US$11.19 billion) to NT$750 billion (US$23.97 billion) but turned out to be only NT$380 billion (US$12 billion) when announced on March 6.

Taiwan’s MND, on February 6, sounded the alarm about three Letters of Offer and Acceptance (LOAs) that are set to expire on March 15. The LOAs, which are for the December sales of Paladin self-propelled howitzers, TOW-2B anti-armor missiles, and Javelin anti-armor missiles, were not signed because of ongoing battles in the LY. MND officials stated they were seeking extensions to the LOAs if a deal was not reached soon. Signing a LOA quickly is an important milestone in the FMS process. A LOA has a payment schedule, whereby Taiwan would pay the U.S. government in installments for the capabilities it is purchasing. The U.S. government negotiates a contract with the defense industry and pays for the capabilities using the funds that Taiwan transfers per the LOA. Importantly, until a LOA is signed and a first payment is made, the Department of Defense cannot enter a contract to produce the weapons. If a LOA is not signed before it expires, then certain steps in the FMS process must be repeated or renegotiated due to potential changes in pricing.

Updates to Abrams, PAC-3 Sales

On February 2, MND officials reported that the final batch of 28 M1A2T Abrams tanks will arrive in Taiwan by the end of March. Delivery of the total 108 tanks has been ongoing since December 2024, when the first batch of 38 arrived in Taiwan.

On February 11, MND officials confirmed to the press that they would be procuring 102 PAC-3 Missile Segment Enhancement (MSE) missiles for Patriot air defense systems, which would be paid via surplus funds from a prior Patriot procurement program.  This is a positive development for the backlog, as the 102 PAC-3 MSEs are a 2022 modification to a 2010 Patriot case and can be funded through surplus from the earlier program. They are separate from and (additive to) the planned but not yet notified Patriot follow-on package (additional batteries and PAC-3 MSEs) expected to be financed through the Lai administrationโ€™s special defense budget.

Amidst these updates, reporting from the Financial Times, New York Times, and Taipei Times has revealed a future arms sale package to Taiwan, including PAC-3 MSE missiles, additional Patriot batteries, Integrated Battle Command Systems, and Lower Tier Air and Missile Defense Sensors radars, all designed to integrate into the Lai administrationโ€™s planned โ€œT-Domeโ€ air defense system. The timeline of this sale, however, is in flux owing to Trumpโ€™s summit with Xi in April.

Trump Administration Announces Arms Sale Reforms

On February 6, the Trump administration launched a new round of arms-transfer reforms through Executive Order 14383 and its accompanying White House fact sheet, establishing an โ€œAmerica First Arms Transfer Strategy.โ€ The order reframes arms transfers as a mechanism for expanding U.S. production capacity, strengthening supply chains, and prioritizing partners that invest in their own defense. The point was reinforced on February 10, when the Pentagon announced the realignment of the Defense Security Cooperation Agency (DSCA) and the Defense Technology Security Administration (DTSA) under the Under Secretary for Acquisition and Sustainment, explicitly tying security cooperation and export administration more closely to defense-industrial management and execution.

At the same time, Taiwan’s arms sales became more visibly entangled with summit diplomacy. Following the February 4 Trumpโ€“Xi call, Beijing publicly urged Washington to handle Taiwan arms sales with โ€œprudenceโ€ and again described Taiwan as theโ€œmost important issueโ€ in U.S.โ€“China relations. Trump then said he was โ€œtalkingโ€ with Xi about future arms sales to Taiwan and would decide โ€œpretty soon,โ€ before the White House promptly clarified that there had been no change in longstanding U.S. policy. Further reporting that a major new package could move only after a Trump trip to China further underscores that dynamic.

Conclusion

Taiwanโ€™s arms sales backlog remained steady at $32.0 billion through the end of February 2026. However, recent developments highlight the role of political factors in the backlog rather than defense industrial capacity.  

The Legislative Yuan has only just begun substantive review of competing special budget proposals, while the March 15 LOA expiration deadline is approaching for several cases notified in December.  Meanwhile, Washingtonโ€™s efforts to streamline arms transfers are occurring alongside high-level diplomacy, which may influence the timing of major new Taiwan FMS notifications to Congress. 

March will be a critical month to determine whether Taipei can turn budget discussions into signed agreements and funding, and whether U.S. process improvements will result in faster execution or be offset by political considerations on both sides.

Taiwan Arms Sale Backlog, January 2026 Update

Special Budget Complications Continue

By Joseph Oโ€™Connor and Eric Gomez

The first month of 2026 was relatively slow for the US arms sale backlog to Taiwan. No new Foreign Military Sales (FMS) were notified to Congress or fully delivered; the topline value of the backlog saw no change since December. Deadlock on the special defense budget in the Legislative Yuan (LY) continued, with the opposition Taiwan Peopleโ€™s Party (TPP) submitting its own, reduced proposal. Additionally, the Department of Defense awarded a contract for the production of F-16 simulators being purchased by Taiwan.

The arms sale backlog as of January 31, 2026, remains $32.0 billion. For arms sales valued at over $1 billion, deliveries in progress are marked in yellow-orange in our visualizations, meaning that the true dollar value is lower than the topline. Figure 1 illustrates the breakdown of the backlog between asymmetric weapons, traditional weapons, and munitions. Table 1 provides an itemized list of all arms sales in the backlog, including the most up-to-date information on their status.

Special Defense Budget Complications

The MNDโ€™s special defense budget, initially announced by President Lai in November 2025, continued its tumultuous journey through the LY in January. The administrationโ€™s proposal, a budget of NT$1.25 trillion (US$40 billion) to be spent over eight years, remained in the LYโ€™s Foreign Affairs and National Defense Committee. Legislators in the Kuomintang (KMT) and Taiwan Peopleโ€™s Party (TPP) โ€” which hold a combined 62 seats to the Democratic Progressive Partyโ€™s (DPP) 51โ€”have prevented Laiโ€™s budget from advancing to the full LY. On January 19, Minister of National Defense Wellington Koo delivered a closed-door, confidential briefing to the Foreign Affairs and National Defense Committee, but little concrete information about the budget was released.

Meanwhile, the TPP announced a counter proposal for the special defense budget, worth NT$400 billion (US$12.69 billion) on January 26 in a press conference, sending it to the LY Foreign Affairs and National Defense Committee for review on January 30. This reduced budget proposal contains funding for five of the eight cases announced in December, including Paladin self-propelled howitzers, HIMARS launchers and munitions, Javelin and TOW anti-tank missiles, and ALTIUS loitering munitions, for a total of NT$311.9 billion (US$9.90 billion). The December FMS cases not funded in the TPPโ€™s proposed budget are tactical mission networks, and spare parts for attack helicopters and Harpoon anti-ship missiles.  The proposal also omitted funding for local partnerships with the Taiwanese defense industrial base, including the procurement of some 200,000 drones. The NT$400 billion represents a spending ceiling, with the LY needing to vote on new funding each year until the total amount is reached. This gives the LY much more oversight power over arms sale spending, giving them multiple opportunities to pause or redirect funding if cases fall behind schedule.

Interestingly, the inclusion of the five most significant cases from December indicates an implicit desire to continue procurement of mostly asymmetric systems. The TPP proposal also includes oversight provisions, including โ€œcomprehensive special reportsโ€ on case statuses over the last five years, how said procurement cases improve joint operational effectiveness, acquisition timelines, and delivery dates, and fiscal impacts. An MND press conference on 26 January refuted these oversight provisions as being time-prohibitive and having effects on the progress of backlogged cases. If passed, however, this level of oversight would provide more effective monitoring of the backlog.

MND Hints at Further Sales

After a Cabinet meeting on 15 January, Vice Minister of National Defense Hsu Szu-chien stated that four more arms sales from the US were in the pipeline, but had yet to be notified to Congress, without giving more details. As of the end of January, it is thought that additional Patriot air defense missile batteries and PAC-3 MSE missiles are one of those sales, but no details have been confirmed by the MND. This, of course, presents more opportunities for the backlog to only grow, but only after these sales have been notified to the U.S. Congress.

F-16 Simulator Contract Awarded

On 29 January, the U.S. Air Force awarded a contract definitization modification valued at US$69.88 million (using US$59.42 million of Taiwan FMS funds) for the procurement of F-16 Block 70 training simulators for the ROC Air Force. This is an extension of a contract originally awarded in January 2023 and appears to be the sixth such extension. Work under the contract is expected to be completed by August 2028, pending further contract extensions. This contract award is part of the US$8 billion F-16 Block 70 sale approved in August 2019.

Other Updates

A few other updates on backlogged cases emerged this month. First, after the 19 January confidential hearing, Minister Koo revealed that from the December sale, 1,554 ALTIUS-700M loitering munitions and 478 ALTIUS-600ISR drones would be procured. This case is worth US$1.1 billion, and previously, the quantity of drones was not specified. Owing to the speed of the first sale of ALTIUS being delivered to Taiwan, we expect this December case to also be fulfilled quickly.

During the month, the MND released details about production line enhancement projects set to be funded under their special defense budget proposal. Among other projects, the 202nd Factory of the MNDโ€™s Armaments Bureau is set to increase 155mm artillery shell production. This affects the recent December sale of Paladin self-propelled howitzers, as those are the only systems in Taiwanโ€™s inventory that would use that caliber of shell. MND sources also stated that surplus 155mm shells would be sold via a partnership with the United States.

On 21 January, the U.S. Army awarded a contract extension worth US$202.78 million (using US$52.38 million in Taiwan FMS funds) to Lockheed Martin for inspection, recertification, and repair of PAC-3 missiles, presumably including missiles in Taiwanโ€™s possession or to be delivered to Taiwan. Similar to the above F-16 contract, this is an extension of a contract originally awarded in June 2022, and work is expected to be completed by June 2028.

Conclusion

January marked the continuation of ongoing budgetary battles in the LY, which have no intention of ending soon, particularly with an opposition alternative being proposed. The special defense budget debate is now the central variable: if the LY cannot reach a workable compromise soon, Taiwan risks procurement delays in the earliest phases of an FMS case. The budget drama also sends mixed signals to allies and adversaries of Taiwan on its willingness to provide for its own defense.  However, the TPPโ€™s emphasis on greater transparency and oversight would be welcome for providing more information about how arms sale cases are progressingโ€”or stalling.