F-16s Remained Delayed, in Shadow of Xi-Trump Summit
Authors: Joe O’Connor, Kayleigh Brown, Denzel Bell, and TSM Staff
September 2026 was a quiet month for the backlog, unlike August. What was thought to be the beginning of F-16 Block 70 delivery in early September resulted in another month of delays; a summit between Xi and Trump in Washington elicited little detail on ongoing or future arms sales to Taiwan. Three cases have minor updates this month, and four major U.S. contracts for backlog-related items or services were awarded this month, marking the end of fiscal year 2026. In September, Congress received no new Foreign Military Sales (FMS) notifications for Taiwan, and no existing sales were fully delivered. The total value of FMS cases notified to Congress but not yet delivered to Taiwan is still $29.72 billion.
Figure 1 shows how the backlog is divided among asymmetric weapons, traditional weapons, and munitions. Arms sales that are only partly delivered are marked in yellow-orange. Table 1 lists all arms sales in the backlog with the latest status updates. Partially delivered sales are shown in italics, while newly announced and fully delivered sales are marked in bold and underlined.
Starting this month, we have also released the arms sale backlog as an interactive tool, providing information on timelines for each case. Check it out here.
F-16 Block 70s Delivery Delayed Further
On September 7, Liberty Times reported that the first two Taiwanese F-16C/D Block 70 fighter jets in delivery to Taiwan (numbered 6727 and 6728) had taken off from Hickam Air Force Base in Honolulu, Hawaii, but returned that same day, for then-unknown reasons. The aircraft remained in Hawaii throughout the entirety of September, with CNA reporting on September 29 that the MND would announce a delivery date once one was confirmed. At that time, Koo stated that Taiwan might receive additional technical support or an extended warranty for the continued delay.

It is our analysis that the F-16s remained delayed during September, including severe weather and typhoon threats in the Western Pacific and generalized maintenance issues. Despite the coincidence of the F-16s eventually being delivered after the Xi-Trump summit in late September, we do not consider the delay to have been “held” or frozen by the administration.
At the time of writing, the two F-16s were delivered to Taiwan on October 2, at approximately 1200 local, per CNA and other Taiwanese media outlets. Since this delivery occurred in October, we will discuss it, along with any future F-16 delivery developments, in the October backlog update.
Trump-Xi Summit Reveals Little on Arms Sales, But Worries Remain
This month featured a bilateral summit between Chinese leader Xi Jinping and President Trump on September 24 in Washington. Consisting mostly of economic policy discussions, arms sales to Taiwan did not feature prominently in the summit, and neither state explicitly mentioned arms sales in their readouts after the meeting.
Before the summit, on September 12, Kyodo News reported that Beijing threatened to cancel the summit if the U.S. approved new arms sales to Taiwan, referring to a potential $14 billion package of equipment. On September 19, CNA reported that Anduril co-founder Palmer Luckey personally raised the stalled package with President Trump, Vice President JD Vance, and Secretary of State Marco Rubio, noting his company’s business with Taipei.
Two days before the summit, on September 22, Reuters exclusively reported that Xi would press Trump on halting new arms sales and pausing current sales in delivery, also invoking the 1982 U.S.-China joint communique. The next day, September 23, Secretary of State Rubio told the press that pending arms sales to Taiwan remain under review as Washington weighs requirements against current stockpiles and production capacity.
As previously stated, the summit day itself featured little to no publicly reported discussion on arms sales. In statements and an interview with Fox News on September 27, U.S. Ambassador to China David Perdue stated that there had been “no change in the Taiwan policy.” Perdue also revealed that during the summit, Trump offered to sell arms to the PRC. The latter statement, reported by the Financial Times, is worrying, but was likely a gaffe on Trump’s part, who later confirmed to the press that he had mentioned it to Xi.
Broadly stated, this represents a continuation of the status quo since last month, and the stalled $14 billion package was originally publicly reported in February 2026. Other commentators, including Zach Cooper at the American Enterprise Institute, stated that based on the summit and planned future summits between Trump and Xi, he “cannot imagine” the Trump administration moving forward with the package until early 2027 at the earliest. While we do not forecast when exactly the package might be notified to Congress, we agree with this assessment, particularly since this latest summit resulted in two additional meetings in 2026, one at APEC in November and again at the G20 in December.
Updates on ALTIUS, MQ-9Bs, MK48 Torpedoes
Various updates also emerged about the following sales this month:
- ALTIUS: On September 10, Liberty Times reported that a prior sale of ALTIUS-600M loitering munitions to the ROC Army arrived in March 2026 without chargers due to the components being made in China, causing U.S. technical personnel to arrive in the country in order to service the systems. This is notable, as a larger batch of over 2,000 ALTIUS-700M and ALTIUS-600ISR unmanned systems are also en route to Taiwan, and issues in their auxiliary supply chains may cause problems in the future if a non-Chinese alternative is not able to be produced quickly.
- MQ-9Bs: On September 14, one of Taiwan’s two delivered MQ-9B SkyGuardian maritime surveillance UAVs was sighted on its first flight near Hualien Air Base in eastern Taiwan. We previously reported that in June 2026, the first two of four airframes were delivered for assembly, testing, and integration in-country by manufacturer General Atomics.
- Switchblade 300 Loitering Missile System: On September 19, UpMedia reported that during familiarity training in Taiwan in August on Switchblade 300 loitering missile systems, several units crashed due to signal disconnection and frequency-hopping issues. In reporting on the Switchblade’s case history, UpMedia also reported that the final batch of Switchblades were scheduled to be delivered by the end of September. At the time of writing, TSM cannot independently verify that claim.
- Mk 48 Heavyweight Torpedoes: On September 23, Zona Militar reported that Mk 48 heavyweight torpedoes could arrive in Taiwan before the end of 2026, allowing additional testing of the indigenously produced Hai Kun submarine to move forward. Citing the president of the Taiwan Security Development Association, this reporting differs from prior reporting from the MND indicating that deliveries would not begin until 2027.
Contract Awards
Four major U.S. contracts involving backlog items were awarded, all by the Air Force, in September:
On September 8, the Air Force awarded Pratt and Whitney, a Raytheon subsidiary, a $19.31 million contract for contractor engineering and support services until organic engineering capability is developed for Taiwan and 10 other FMS customers. Work is expected to be completed by March 2029. TSM estimates that these services likely apply to Taiwan’s existing fleet of F-16A/B Block 20 fighter jets, which have Pratt and Whitney-manufactured engines.
On September 22, the Air Force awarded Raytheon a $105.65 million contract modification for Advanced Medium-Range Air-to-Air Missile (AMRAAM) parts purchases. This is an extension of a contract originally awarded in September 2025 and involves Taiwan alongside 28 other FMS customers. Work is expected to be completed by August 2027. In August, we reported that the initial batch of 200 AMRAAMs was in delivery to Taiwan.
Six days later, on September 28, the Air Force also awarded Raytheon a $20.70 billion undefinitized contract action for AMRAAM all-up rounds and guidance section procurement. This action involves FMS sales to Taiwan and 15 other customers. Work is expected to be completed by June 2033. An undefinitized contract action means that a final contract or price has not been confirmed, but authorizes production.
On September 30, the U.S. Air Force jointly awarded 21 companies a $2.4 billion total contract for repair, overhaul, and manufacture of parts for F100-PW-220/229 aircraft engines. This contract involves FMS sales to Taiwan and 28 other countries. Work is expected to be completed by September 2036. The F100-PW-220/229 engine is used in F-15 and F-16 fighter jets.
| Table 1 | |||
| Itemized list of backlogged capabilities by weapons category, September 2026 | |||
| Capability Sold | Dollar Value (In Millions) | Share of total backlog, September 2026 | Current Status as of September 2026 |
| Traditional | $14,927 | 43.50% | |
| F-16C/D Block 70 | $8,000 | 26.92% | September 2026: Taiwanese media reports first two jets (6727 and 6728) took off from Hickam AFB in Hawaii, then returned. Jets remained in Hawaii, MND stated it would provide update on delivery date. |
| Paladin Self-Propelled Howitzer | $4,030 | 13.56% | May 2026: Liberty Times reports that deliveries of Paladins are expected to start in 2030, due to U.S. production delays. |
| F-16 IRST Systems | $500 | 1.68% | December 2025: US DoD awarded an undefinitized contract action to Lockheed Martin for targeting pods, including 55 IRST pods for Taiwan. Work is expected to complete by June 2031. |
| MS-110 Recce Pods | $367 | 1.24% | August 2026: Pod sighted on F-16V around Jiashan Air Base, Taitung, undergoing first test of pod since arriving in Taiwan. |
| MK 75 76mm Gun Mounts | $30 | 0.10% | No information since posting of Congressional notification. |
| Asymmetric | $14,763 | 48.67% | |
| HIMARS (Announced December 2025) | $4,050 | 13.63% | April 2026: MND issues procurement contract for “long-range precision strike systems,” likely meaning HIMARS, worth US$3.92 billion, with estimated completion in December 2032. Lockheed Martin also received a contract for full-rate production of launchers for U.S. and FMS customers, including Taiwan. |
| Harpoon Coastal Defense System | $2,370 | 7.97% | August 2026: MND made final award for contract to transport HCDS equipment from US to Taiwan, worth $7.8 million and expected between August 2026 and July 2028. |
| National Advanced Surface-to-Surface Air Missile System (NASAMS) | $1,160 | 3.90% | February 2026: Press reports citing MND sources repeated earlier reporting that Taiwan plans on purchasing 9 additional NASAMS systems and associated missiles. This appears to be one of the arms sales cases being held up by special procurement budget deadlock in the LY. |
| ALTIUS (Announced December 2025) | $1,100 | 3.70% | August 2026: MND signs LOA for purchase of 1,554 700M loitering munitions and 478 600M ISR drones, finalizing deal. |
| Tactical Mission Network | $1,010 | 3.40% | January 2026: LY votes to move a special procurement budget proposed by the TPP to committee for consideration. The bill would not fund the Tactical Mission Network, but would fund almost all other FMS cases notified to Congress in December 2025. |
| PAC-3 MSE Interceptors | $882 | 2.97% | March 2026: MND officials stated that ongoing delivery of 102 MSE missiles should not be affected by conflict in the Middle East. |
| AN/TPS-77 and AN/TPS-78 Radar Systems | $828 | 2.79% | September 2025: Taiwanese press report citing 2026 budget request says that all radar systems will be delivered by the end of 2028. TPS-77s scheduled to begin arriving in 2026; TPS-78s to begin arriving in 2027. |
| MQ-9B Unmanned Aircraft | $600 | 2.02% | September 2026: Taiwanese media reported sighting first flight of MQ-9B from Hualien Air Base, out of two total that were assembled and tested in-country by General Atomics. |
| HIMARS (Announced December 2022) | $520 | 1.75% | June 2026: Included in MND force structure plan, 18 launchers expected “soon,” consistent with reporting from February 2026. |
| Javelin Missiles | $375 | 1.26% | April 2026: MND issues procurement contract for “anti-armor missiles,” likely meaning Javelin or TOW-2B missiles, worth US$162.75 million, with estimated completion in September 2030. |
| Air-Launched Harpoon Missiles | $355 | 1.19% | January 2023: Press report indicates that missiles will be delivered by 2030. |
| TOW Missiles | $353 | 1.19% | April 2026: MND issues procurement contract for “anti-armor missiles,” likely meaning Javelin or TOW-2B missiles, worth US$162.75 million, with estimated completion in September 2030. |
| Field Information Communications System | $280 | 0.94% | June 2026: Taiwanese media reported on immediate combat readiness exercises featuring FICS-equipped vehicles alongside combat units. Reporting also indicated ROCA units had begun fielding FICS systems in February 2026, though it is unclear whether all have been delivered. |
| C4 Modernization | $265 | 0.89% | No information since posting of Congressional notification. |
| Volcano Anti-Tank Mining System | $180 | 0.61% | June 2026: Included in MND force structure plan, full order of 14 systems expected to ship “soon,” then be organized into “mobile interdiction teams” once in Taiwan, consistent with prior reporting. |
| Taiwan Advanced Tactical Data Link System Upgrade | $75 | 0.25% | August 2024: Taiwan’s E-Procurement System announced the award of a contract for the Link-16 system with completion date in 2026. |
| Switchblade 300 Loitering Missile System | $60 | 0.20% | September 2026: Taiwanese media reports that several Switchblades crashed during familiarity training in August, due to frequency-switching and signal disconnection errors. Same report also indicated final batch of Switchblades could arrive by end of September. |
| Munitions | $2,329 | 7.84% | |
| AGM-84H SLAM-ER Missile | $1,008 | 3.39% | December 2025: Taiwanese press report citing a publication by the LY’s budget office indicates a multi-year delay in finalizing details on cost and delivery schedule for AGM-84 missiles. Press report suggests that there is no finalized Letter of Offer and Acceptance (LOA) for this case, which would lay out a payment and delivery schedule. |
| F-16 Munitions | $619 | 2.08% | August 2026: Liberty Times reports that all 100 AGM-88 HARM missiles have been “deployed,” and that AMRAAM missiles have also been delivered “in batches.” |
| Mk 48 Heavyweight Torpedoes (Announced June 2017) | $250 | 0.84% | September 2026: Reporting citing Taiwanese think tank states Mk 48s should begin delivery by the end of 2026, allowing further Hai Kun testing. |
| AGM-154C Joint Standoff Weapon | $186 | 0.62% | August 2026: Liberty Times reports that JSOW delivery continues to be delayed until “between 2027 or 2028.” |
| Mk 48 Heavyweight Torpedoes (Announced May 2020) | $180 | 0.61% | September 2026: Reporting citing Taiwanese think tank states Mk 48s should begin delivery by the end of 2026, allowing further Hai Kun testing. |
| AIM-9X Block II Missiles | $86 | 0.29% | August 2026: Liberty Times reports that an “initial batch” of AIM-9X Block IIs have been delivered, out of a total of 140. This is an increase of 40 missiles from the initial Congressional notification. |